4-INSTALLATION AND ASSEMBLY
PRODUCT INLET HOLE
The hole to be made in the wall must be 765*610 mm. These measurements allow the frame to cover the gap that remains between the
product and the hole and also allow the product to be removed if maintenance is to be performed and/or parts are to be replaced.
SWITCH AND CONTROL PANEL CONNECTION
The emergency panel and switch are already fitted on the pellets loading door and are already connected to the relative cables by the
manufacturer. Take the switch cable and connect it to the socket on the rear of the product.
The control panel must instead be connected to the circuit board in position 1.
• Pay utmost attention when handling panels connected to the relative cables.
• Cables must stay in areas away from heat or in areas where they cannot be damaged in the event of extracting
the product.
• For proper operation make the flat cable and the switch cable pass far from each other, with different paths.
• Do not force insertion of the connector under any circumstances.
• Do not fold and/or twist the cables.
• Do not modify the connectors or cabling or panel supports.
DOOR ASSEMBLY
Once the electrical cabling is complete, before fixing the hood door permanently, carry out an operation test.
If the test has a positive outcome, fix the door to the hood with four screws, using the four holes present on the door frame and indi-
cated with the letter (B).
The holes indicated on the horizontal profiles of the door (A) are instead for fixing the door frame to the chute frame to permanently
fasten the two elements, enclosing the hood wall in the middle.
One must preventively make a rectangular hole in the hood at a height determined by how the optional support has been installed or by
how the brickwork platform has been constructed.