4-INSTALLATION AND ASSEMBLY
Technical Dept. - All rights reserved - Reproduction is prohibited
PELLET LOADING CHUTE ASSEMBLY
Another decision to be made before positioning the product is to define the side on which to install the chute for loading fuel. The pel-
lets fuelled Vivo 80 Hydro is delivered with two clamps, the connection pipe and chute with hatch.
The chute can be fitted on the right side, on the left side or frontally. The connection pipe is 1 metre long.
It is mandatory
to shorten the connection pipe, depending on its positioning (side or front), so that it is well taut and
forms a minimum angle with respect to the horizontal as shown in the drawing. This operation is necessary for the pellets'
descent.
Before setting up the cladding carry out a fuel loading test to assess its proper descent towards the hopper.
It is mandatory to insulate the pipe properly in the event this is fitted on the left side in correspondence of the smoke evacu-
ation duct. Fire hazard!
Chute assembly
In the event one decides to position the pipe laterally, the distance from the machine axis to the wall must be at least 80 cm (figure
shown here).
To position the chute act as follows:
• Connect the supplied pipe to the product paying attention that it is rotated sideways, and fasten it with the clamp.
• Connect the pipe (in the upper part) to the opening of the door structure with the supplied clamp.
• Position the pipe with the door structure so that, when the cladding is complete, one can screw and fasten it to the cladding wall in
correspondence of the hole made for its insertion.
• To assemble the external door, which must only be done when the cladding is complete, refer to the relative section.