Ref.: WB-VL-65 DSP LX Premium - OM Ver.1.6 (B2927)
10
4.3.
FOUNDATION
Proof of safe floor load capacity is the owner's responsibility
strongly recommended to install Wheel balancer using Foundation bolts.
Failing to comply may lead to toppling of cabinet & damage to equipment.
Manufacturer will not be responsible for non-compliance
1.
Place the Cabinet at designated location & mark its foundation fixing holes.
2.
Move the Cabinet. Bore the marked holes using a Hammer drilling machine
equipped with a 12mm concrete drill bit to required depth in the floor considering
the foundation bolt length with sufficient length above the floor level for fixing
cabinet. Clean the dust in the foundation area and holes.
3.
Insert the M12x125mm Lg. Anchor bolt into the holes. Insert the foundation pin
into the Anchor bolt and hammer to lock it.
4.
Place the cabinet over the Foundation bolts by providing M16 Spring washer
(Flat type) between the Cabinet and Floor.
5.
Fix the Cabinet with foundation bolts using Nut & Washer that comes along with
Anchor bolt.
6.
Check of any tilt. Use required quantities & thickness of „U‟ type shims (0.5mmT
& 1.0mmT
)
in between the Spring washer & Floor for compensation, if required.
Fig. 3
4.4.
INTEGRATION
4.4.1.
MONITOR
1.
Fix the Monitor column with Main
cabinet at the rear side (Centre)
using respective Allen screw &
Spring washer (2 Nos.) each.
Ensure the column is
perpendicular to the Cabinet.
2.
Fix the Monitor with Monitor
plate using WH-PH screw (4
Nos.) firmly and ensure the
straightness.
3.
Connect one end of the Monitor
power cord with Monitor and
other end to the socket provided
at rear (Right) side of cabinet.
4.
Connect the HDMI end of
Monitor cable from the SBC
(Raspberry Pi) board with Monitor.
Fig. 4
5.
Verify all the connectors are proper and without any loose contact. Close
the Top cover.
Nut for
Anchor bolt
Washer for
Anchor bolt
Cabinet base
Shim
Spring washer
Top
cover
Monitor
cable
routing
cutout
Monitor
Monitor
column
Monitor
plate
Monitor
power
socket