Ring Setup and Testing: Integration Procedures
Fiber Installation
6 - 8
Lucent Technologies - Proprietary
See notice on first page
365-372-327 R2.0
Issue 1, October 2003
............................................................................................................................................................................
Step 19
Verify proper shelf timing at each node using
RTRV-SYNCN. Set the
timing to internal at
LT-DMXTEND
-1 and line time
LT-DMXTEND
-2.
This is done through the SET-SYNCN command.
............................................................................................................................................................................
Step 20
In order to verify proper communications with the adjacent
Metropolis
®
DMXtend nodes, execute the following command from
the
Command Builder
.
RTRV-MAP-NEIGHBOR
Result:
The TIDs and NSAPs of adjacent nodes will be displayed
along with the OLIU and port they are connected to.
............................................................................................................................................................................
Step 21
In order to verify proper network DCC communications, execute the
following command from the
Command Builder
.
RTRV-MAP-NETWORK
Result:
The TIDs and NSAPs of all the nodes in the TARP area will
be displayed.
............................................................................................................................................................................
Step 22
Perform steps in this procedure on all adjacent nodes in the ring.
............................................................................................................................................................................
Step 23
After all connections and tests have been made, verify optical fiber
cables are placed in the fiber slots on the left side of the shelf and
properly routed in bay framework.
............................................................................................................................................................................
Step 24
Check off the appropriate box in Appendix E, Installation Checklist.
...........................................................................................................................................................................
End of Steps