Lucent Technologies Lineage
®
2000 ECS Battery Plant J85500D-3
Issue 5 January 1999
Installation 4 - 5
To ensure personnel safety and equipment protection use
appropriate equipment during handling of crates and uncrated
equipment. Use the equipment weights and dimensions, given in
Section 2, as a guideline for choosing material handling tools.
Move crated equipment to an area with adequate space and tools
for unpacking and handling.
Carefully open the packaging to verify that the contents are
complete and undamaged. If the equipment must be returned, it
should be repacked in the original shipping crate.
WARNING:
Do not connect batteries to the system at this time.
Step B: Battery
stand assembly
Assemble battery stands per the battery manual. Install the
batteries onto their stands.
Step C: Cable
support and
ground system
Hang all cable support systems, as well as any auxilliary ground
bus bars, as dictated by the job application drawings.
Step D:
Controller and
LVD set-up
Follow the controller set-up procedure given in the Controller
manual to complete the steps below.
1. Enable/disable equalize charge set-up
2. Enable/disable rectifier restart set-up
3. Set HV shutdown level(s)
4. Set BD alarm level
5. Run office alarm wiring
6. Run other controller wiring
7. Set up other optional circuit packs
Check and set the low-voltage battery disconnect/reconnect, if
provided, at the desired voltage level. See Figure 4-4a for the
location of the disconnect voltage select jumpers, J505.1 and
J505.2 on LVD/Fuse Board. Plug these jumpers across pins 1
and 2 of their respective connectors to provide a disconnect