394149/D
173
Securing and terminating cables
Once a cable has been prepared for termination, it must be connected to a unit or cabinet.
Prerequisites
Electrical installations can only be done by certified electricians. All necessary tools and
instruments required must be available. The installation shipyard must prepare detailed
drawings of the electrical system, and identify each cable.
Context
Observe the relevant cable plans, cable lists and/or interconnection drawings for the
EK80.
Procedure
1
Referring to the wiring diagram and ensuring that there is 5 to 10 cm slack cable
inside the cabinet, prepare and connect the cable cores to the appropriate terminals
and/or plugs within or onto the cabinet.
2
Secure the cable using cable clips.
3
Check the terminal connections against the wiring diagram to ensure they are
correct. Follow the same procedure for all the cables and cable glands.
4
Check the cabinet to ensure all tools and rubbish are removed, then close the
cabinet door.
5
Take the appropriate safety measures, then replace the fuses and apply power to
the system.
6
Perform a relevant system test to ensure the installation has been made successfully.
Related topics
Basic cable requirements, page 167
Cable glands and termination procedures, page 170
Cable layout and interconnections, page 85
Summary of Contents for Simrad EK80
Page 1: ...kongsberg com simrad Simrad EK80 INSTALLATION MANUAL ...
Page 2: ......
Page 12: ...10 394149 D Simrad EK80 ...
Page 313: ...394149 D 311 Drawing file ...
Page 314: ...312 394149 D Simrad EK80 Installation Manual ...
Page 317: ...394149 D 315 Drawing file ...
Page 318: ...316 394149 D Simrad EK80 Installation Manual ...
Page 320: ...318 394149 D 201575 Transducer connector assembly and wiring Simrad EK80 Installation Manual ...
Page 352: ... 2020 Kongsberg Maritime ISBN 978 82 8066 182 1 ...
Page 353: ......
Page 354: ...Installation Manual Simrad EK80 ...