Lifting machine
Fit wire rope (cable) to lifting holes (2) in the bracket
installed to the mounting hole of the counterweight and
boom foot pin (1).
q
Lifting weight: 26.5 tons
(a): Pin diameter at lifting position
∅
140 mm
(b): Hole diameter at lifting position
∅
75 mm
(c): 2782 mm
2.
The mark for the center of gravity installed to the machine
shows the position of the center of gravity in the condition
shown in the diagram on the right.
(d): Distance between centers (horizontal) measurement
4507mm
3.
Combination of wire rope (cable) length
The length of wire rope (cable) is the length from the pin to center of the hole.
q
When using the following wire rope, use wire rope with more length than given in chart below.
q
In addition, select a wire rope length that will bring the lifting position directly above the center of gravity of
the machine.
4.
After the machine comes off the ground, check the hook condition and the lifting posture, and then lift slowly.
Combination
(A)
6.8m
(B)
8m
Summary of Contents for Galeo PC800LC-8
Page 2: ......
Page 3: ...FOREWORD 11 ...
Page 16: ...PRODUCT INFORMATION FOREWORD 1 14 ...
Page 24: ...CONTENTS 1 22 ...
Page 29: ...SAFETY SAFETY LABELS 2 5 LOCATION OF SAFETY LABELS 2 ...
Page 64: ...SAFETY MAINTENANCE INFORMATION SAFETY 2 40 ...
Page 220: ...TROUBLES AND ACTIONS OPERATION 3 156 ...
Page 301: ...SPECIFICATIONS 15 ...
Page 304: ...SPECIFICATIONS SPECIFICATIONS 5 4 ...
Page 313: ...INDEX 17 ...
Page 314: ...INDEX 7 2 ...
Page 317: ...COLOPHON 18 ...