SECTION 4 - MACHINE OPERATION
3121773
– JLG Lift –
4-21
4.9
BATTERY CHARGING - LITHIUM-ION MACHINE
To check the battery condition on the lithium
ION equipped machine, power up the
machine and use the special indicator shown
at position 8 on the platform control station
LCD display.
or;
Check charge indicator
(item 2)
on
top right side of the Lithium-Ion bat-
tery pack.
While charging,
this indi-
cator shows the current charge state
of the lithium-ion battery pack as fol-
lows;
RED LED: shows that the battery is in
the initial charging phase.
YELLOW LED: shows that the battery has reached 80%
charge.
GREEN LED: shows that the battery has reached 100% of
charge.
If machine is powered on while charging, the
LCD display on the platform control station
also shows the machine charge indicator.
Charging the Battery Pack
DO NOT LEAVE THE MACHINE IN CONTINUOUS CHARGING FOR TIME PERIODS
EXCEEDING 24 HOURS.
REMEMBER, THE CHARGE WORKS EVEN IF THE ELECTRONIC BOARD OF THE
MACHINE IS TURNED OFF. SO THE BATTERIES CAN BE CHARGING EVEN IF THE
REMOTE CONTROL IS OFF.
CHARGE THE MACHINE USING ONLY THE BATTERY CHARGER INSTALLED ON
IT. THE USE OF A CHARGER OTHER THAN THAT PROVIDED VOIDS ANY KIND
OF WARRANTY ON BATTERIES.
Approximate time required to fully recharge the battery
pack:
•
Full Recharge -8 hrs. - 120V AC or 4 hrs. - 220V AC
•
80% Recharge -4 hrs. - 120V AC or 2 hrs. - 220V AC
•
The batteries can be charged during machine opera-
tion,
(obviously the charging times in this case will be lon-
ger)
.
•
The batteries can be charged when they are not fully
depleted.
•
If the charge is less than 20% an audible
warning signal and an icon will be acti-
vated whenever the electric motor is
started, to alert the user to charge the
machine.