2.3. Double Sided Timing Belt and Drive Pulleys
a)
Removal
•
Disconnect
the
power cord
from the machine.
1. Remove the
conveyor pulley
,
motor belt
and the
gears
. (See Section 2.2)
2. Remove the
double sided belt
.
a) Loosen the
idler tension bracket
and slide the bracket and pulley down to release tension on the belt.
b) Remove the
idler pulley
from the bracket.
Note:
The
pulley
uses a double screw attachment and both sides must be held to unscrew the screws.
3. Remove the
roll pulleys
.
a) Loosen the set screws and remove the
pulleys
.
4. Remove the
belt.
b)
Installation
1. Installation is the reverse of removal.
Summary of Contents for 7K Plus
Page 2: ...ii...
Page 31: ...31 11 Appendix Side Frame Assembly Drawings...
Page 33: ...33 7KPlus Exploded Drive Train...
Page 34: ...34 10 Amp IEC Bracket Assy IEC Outlet...
Page 36: ...36 Retard Assembly...
Page 37: ...37 7KPlus Schematic...
Page 38: ...38...
Page 51: ...51...
Page 52: ...52 Phone 866 427 4546 Fax 603 332 8043 www brilininc com...