Table 40. Electrical
1
Electrical characteristics
Properties
Power source loading maximum in kVA
For more information about rack power distribution
units and power cord options, see Power distribution
unit and power cord options for 7014 racks.
1
The total rack power can be derived from the sum of the power that is used by the drawers in the rack.
See your individual server or hardware specifications for temperature and humidity requirements.
Rack noise levels depend on the number and type of drawers installed. See your server or hardware
specifications for specific requirements.
Note: All rack installations require careful site and facilities planning that is designed to both address the
cumulative drawer heat output and provide the airflow volume rates necessary to comply with drawer
temperature requirements. All rack installations require careful site and facilities planning that is
designed to address both the cumulative drawer heat output and provide the airflow volume rates
necessary to comply with drawer temperature requirements. Rack airflow requirements depend on the
number and type of drawers installed.
Note: Acoustic doors are available for IBM racks. Feature code 6248 is available for 7014-T00 racks.
Feature code 6249 is available for 7014-T42 racks. The overall sound reduction is approximately 6 dB.
The doors add approximately 381 mm (15 in.) to the depth of the racks.
Service clearances
Table 41. Service clearances for 7014-T00 and 7014-T42 racks
Front
Rear
Sides
915 mm (36 in.)
915 mm (36 in.)
915 mm (36 in.)
Note: Recommended minimum vertical service clearance from the floor is 2439 mm (8 ft).
Figure 3 on page 32 provides the caster and leveler locations for 7014-T00 and 7014-T42 racks.
Site and hardware planning 31
Summary of Contents for 9008-22L
Page 1: ...Power Systems Site and hardware planning IBM...
Page 4: ...iv...
Page 14: ...xiv Power Systems Site and hardware planning...
Page 16: ...2 Power Systems Site and hardware planning...
Page 20: ...6 Power Systems Site and hardware planning...
Page 40: ...Figure 1 FC EPB8 power distribution panel 26 Power Systems Site and hardware planning...
Page 49: ...Figure 5 FC ERG0 rear rack extender top down view Site and hardware planning 35...
Page 123: ...Figure 35 Cable management bridge lances Site and hardware planning 109...
Page 163: ......
Page 164: ...IBM...