background image

 
 

© Copyright IBM Corporation 2020.               Customer Install Guide, PDU 

63 

Electronic Emissions Notices 

Class A Notices 

The following Class A statements apply to IBM products and their features unless 
designated as electromagnetic compatibility (EMC) Class B in the feature information. 
When attaching a monitor to the equipment, you must use the designated monitor cable 
and any interference suppression devices supplied with the monitor. 
United States Federal Communications Commission (FCC) Notice 
 
This equipment has been tested and found to comply with the limits for a Class A digital 
device, pursuant to Part 15 of the FCC Rules. These limits are designed to provide 
reasonable protection against harmful interference when the equipment is operated in a 
commercial environment. This equipment generates, uses, and can radiate radio 
frequency energy and, if not installed and used in accordance with the instruction 
manual, may cause harmful interference to radio communications. Operation of this 
equipment in a residential area is likely to cause harmful interference, in which case the 
user will be required to correct the interference at his own expense. 
 
Properly shielded and grounded cables and connectors must be used in order to meet 
FCC emission limits. Proper cables and connectors are available from IBM-authorized 
dealers. IBM is not responsible for any radio or television interference caused by using 
other than recommended cables and connectors or by unauthorized changes or 
modifications to this equipment. Unauthorized changes or modifications could void the 
user's authority to operate the equipment. 
 
This device complies with Part 15 of the FCC rules. Operation is subject to the following 
two conditions: 

(1) this device may not cause harmful interference, and (2) this device must accept 

any interference received, including interference that may cause undesired 
operation. 
 

 

 

Responsible Party: 

 

 

 

International Business Machines Corporation 

 

 

 

New Orchard Road 

 

 

 

Armonk, NY 10504 

 

 

 

Contact for FCC compliance information only: [email protected] 

      

 

 

 

Der verantwortliche Ansprechpartner des Herstellers in der EU ist: 

 

 

 

IBM Deutschland GmbH 

 

 

 

Technical Relations Europe, Abteilung M456 

 

 

 

IBM-Allee 1, 71139 Ehningen, Germany 

 

 

 

Tel: +49 (0) 800 225 5426 

Summary of Contents for 3454-FCE

Page 1: ...nstall Guide Power Distribution Unit PDU 3454 FCE FCG Version 1 3 Note Before using this information and the product it supports read the information in Safety notices on page 7 Notices on page 68 the...

Page 2: ...Guide PDU 2 This edition applies to IBM Cloud Pak for Data System Components February June 2020 Copyright IBM Corporation 2020 US Government Users Restricted Rights Use duplication or disclosure restr...

Page 3: ...anning 17 PDU loading 17 Plan for redundant power 17 Plan for power outages 20 Plan an emergency power off switch 20 Ground or earth your system 20 Contact an electrician 20 Control Ports 20 Control P...

Page 4: ...ting the PDU to a console 43 Connecting the PDU to a LAN 44 Connecting output devices 45 Configuring the PDU via serial COM port 46 COM Port setup 46 Log In 47 Setting the IP Address 48 Receptacle con...

Page 5: ...PDU 5 Viewing the history log 59 Viewing the event log 60 Resetting the PDU 61 Password reset 61 Reset to factory defaults 62 Electronic Emissions Notices 63 Regulatory and Compliance 67 Notices 68 C...

Page 6: ...Copyright IBM Corporation 2020 Customer Install Guide PDU 6 Safety...

Page 7: ...tention notices call attention to the possibility of damage to a program device system or data World Trade safety information Several countries require the safety information contained in product publ...

Page 8: ...ent or additional copies of safety information documentation can be obtained by calling the IBM Hotline at 1 800 300 8751 German safety information Das Produkt ist nicht f r den Einsatz an Bildschirma...

Page 9: ...tructed otherwise in the installation and configuration procedures Disconnect the attached AC power cords turn off the applicable circuit breakers located in the rack power distribution panel PDP and...

Page 10: ...on top of rack mounted devices In addition do not lean on rack mounted devices and do not use them to stabilize your body position for example when working from a ladder Each rack cabinet might have m...

Page 11: ...time The rack might become unstable if you pull out more than one drawer at a time For fixed drawers This drawer is a fixed drawer and must not be moved for servicing unless specified by the manufact...

Page 12: ...raised to their highest position Ensure that there is no stabilizer bracket installed on the rack cabinet during movement Do not use a ramp inclined at more than 10 degrees When the rack cabinet is i...

Page 13: ...vices are not to be used as shelves or work spaces Do not place objects on top of rack mounted devices In addition do not lean on rack mounted devices and do not use them to stabilize your body positi...

Page 14: ...08 CAUTION This part or unit is heavy but has a weight smaller than 18 kg 39 7 lb Use care when lifting or installing this part or unit C008 Japan Product Safety Notifications English translation If t...

Page 15: ...PDU 3454 FCE FCG 13 03GJ009 Customer Install Guide 1U Chassis 3455 XXX 14 29R2409_Important_Notices 15 G229 9054 IBM Systems Safety Notices translations Pub These documents contain important safety a...

Page 16: ...e included 4 point mounting kit PDUs can utilize different input power cords to accommodate various power types See individual descriptions for a table of power limitations and plug types All Cloud Pa...

Page 17: ...the individual Cloud Pak for Data System building blocks or in the IBM Site Survey Verify all information by cross checking with the rating labels located on the equipment in the rack The power loadin...

Page 18: ...Pak components are sized to stay at or below the 10 amp C13 receptacle limit figure 2 See figures 3 and 4 for typical redundant PDU install and connection to Cloud Pak building blocks See figure 5 for...

Page 19: ...Copyright IBM Corporation 2020 Customer Install Guide PDU 19 Figure 4 Dual PDUs for redundant power Figure 5 Align PDUs as shown to differentiate between left and right redundant power...

Page 20: ...your Power Information Table IBM installers can also share reference wiring diagrams to clarify your power sizing needs Note that IBM installers will do the in rack power and signal cabling once the...

Page 21: ...k Temperature 18C 27C 61F 80F 10C 35C 50F 95F 1 5 5C 45C 41F 113F Humidity 25 60 noncondensing 2 4 20 80 noncondensing 2 4 8 85 4 Maximum Operating Altitude 3050m 10 000 ft 1 Shipping Temperature 40C...

Page 22: ...ed default line cord for standard data center receptacles worldwide These default cords accommodate 30 32A single phase and are noted in the first column of Table 4 below Table 4 3454 FCE Single phase...

Page 23: ...V ac 30 A plug 24 A derated Single phase 4 3 m 14 ft NEMA L6 30 2P G Plug type NEMA L6 30P Wall receptacle type NEMA L6 30R Mating connector Type NEMA L6 30C 4 800 watts after derating United States...

Page 24: ...cord as noted in the first column of Table 5 below Table 5 3454 FCG 3 phase delta power cords Line Cord Part Number Description Voltage Amperage Phase Length Wall plug IBM shipped plug Female wall and...

Page 25: ...ture of our IBM power cords The specifications the components used in the design and the manufacturing process is an external safety agency approved process that is audited by safety agencies on a per...

Page 26: ...appropriate Service Delivery and Field Marketing Practices personnel Definition of an alteration An alteration is any change to an IBM machine that deviates from IBM physical mechanical electrical or...

Page 27: ...that the rack in which you plan to install the system meets the space requirements outlined in Figure 6 Figure 6 Top down view of installed PDU with 4 point horizontal mounting Location in the Rack Th...

Page 28: ...1U Blank Panel 29 1U Blank Panel 28 1G Switch 27 1U Blank Panel 26 1U Blank Panel 25 25G Switch 24 1U Blank Panel 23 1U Blank Panel 22 1U Blank Panel 21 1U Blank Panel 20 1U Blank Panel 19 1U Blank Pa...

Page 29: ...location see Figure 7 for recommended switch location U27 PDUs Install horizontally at U33 U34 for easy cable routing and service access Additional PDUs should be installed above the PDUs at locations...

Page 30: ...Blank Panel 23 1U Blank Panel 22 1U Blank Panel 21 1U Blank Panel 20 1U Blank Panel 19 1U Blank Panel 18 1U Blank Panel 17 1U Blank Panel 16 1U Blank Panel 15 Chassis 5 14 13 1U Blank Panel 12 Chassis...

Page 31: ...6 30 or IEC309 32A P N E PDU Installation Procedure Pay Attention All components must have the same airflow direction when installed in the rack Cold air enters at the front of the rack and exits at t...

Page 32: ...to the PDU with two M3x5 screws B per bracket Use screws that were provided with the rack mounting kit Ref Figure 9 Figure 9 Aligning the vertical mounting brackets to the front of the PDU PDU picture...

Page 33: ...nuts instead of nut clips to the specified EIA locations Use cage nuts that were provided with the rack mounting kit 5 Hold the PDU model at a slight angle and carefully insert it into a mounting spa...

Page 34: ...PDU from the rack frame e Position the marks on the rails so that they are at the rear of the PDU f Tighten the M3 pan head screws that secure the long mounting brackets to the PDU g Hold the PDU mode...

Page 35: ...e following steps a Adjust the long mounting brackets to fit the depth of the rack cabinet b Tighten the M3 pan head screws that secure the long mounting brackets to the PDU c Make sure that the long...

Page 36: ...del Disengage the PDU circuit breakers by pulling the six PDU circuit pins away from the PDU chassis receptacle side Figure 13 then connect the power cord to the PDU Align the connector on the power c...

Page 37: ...connect the power device to an authorized power source for that device 13 Connect the power cord to a properly wired and grounded dedicated power source IBM Installers will connect the components in...

Page 38: ...a single EIA vertical mounting space in the side of the rack complete the following steps Procedure 1 Read the Rack safety notices Pub G229 9054 included with the unit 1 Align the vertical mounting b...

Page 39: ...attach the PDU model Use nut clips that were provided with the rack mounting kit See the following Figure 15 Figure 15 Attaching nut clips to the rack mounting flanges from the rear of the rack 4 Ali...

Page 40: ...he power source wall before you connect or disconnect the input power cord from the PDU model 5 Disengage the PDU circuit breakers by pulling the six PDU circuit pins away from the PDU chassis recepta...

Page 41: ...ce toward the rear of the rack and secure the power cord with the cable straps that are provided with the PDU model 7 Route the power cord toward a dedicated power source Use the provided cable straps...

Page 42: ...es before powering on the system 9 If you removed the side covers or doors reinstall them ALL OPEN RACK BAYS REQUIRE FILLERS TO PREVENT HOT AIR FROM RECIRCULATING TO THE FRONT OF THE RACK AND INTO THE...

Page 43: ...ing a notebook computer to a 1U PDU If your workstation or notebook computer does not have a DB9 serial connector you can use a DB9 to USB converter cable to connect the PDU to a workstation or notebo...

Page 44: ...ion is now established with the PDU through the COM port that is created by the converter cable Connecting the PDU to a LAN You can use a LAN connection to monitor the PDU power outlets and digital ou...

Page 45: ...nect devices such as workstations servers and switches You can monitor the power status of a connected device either manually or remotely through the RS 232 Serial port and Ethernet Ethernet port conn...

Page 46: ...ing the following steps Once the serial cable has been connected per the earlier procedure start a serial COM session using a program such as Putty The complete list of port settings for a serial COM...

Page 47: ...ion is open press Enter Figure 21 Initial Telnet Window Log In The IBM PDU Configuration Utility login window opens The default login ID is Admin press Enter The default password is 00000000 press Ent...

Page 48: ...to an Ethernet network with a DHCP server an IP address will automatically be assigned Check your router for connected clients and to identify the IP address assigned The default name for the device...

Page 49: ...e configuration PDU circuit breakers shown to the right must be fully engaged pressed in before configuring the outlets The PDU location and receptacle information can be changed for the PDU Press 3 e...

Page 50: ...stomer Install Guide PDU 50 Figure 26 Set PDU Location and Outlet Information The instantaneous real time voltage amps watts and relay status on or off can be displayed Press 2 and then Enter See Figu...

Page 51: ...ects power to IT equipment in the event of an emergency such as electrocution fire or flood Figure 28 Set Outlet Status To choose the EPO parameters press 4 enter T1 is the wait delay in seconds befor...

Page 52: ...Copyright IBM Corporation 2020 Customer Install Guide PDU 52 Figure 29 EPO Setup...

Page 53: ...interface complete the following steps 1 Start a web browser from a workstation or notebook computer and enter the IP address of the PDU in the address field The Connect to window is displayed See Fi...

Page 54: ...tored probe the temperature and humidity environment conditions are displayed Figure 31 Main menu of the WEB utility Changing the basic settings Use the Network Access menu to configure the PDU system...

Page 55: ...m menu See Figure 33 To view the information of the PDU and Web SNMP card complete the following steps 1 From the main status page in the left navigation pane click System 2 Click Hardware Firmware In...

Page 56: ...Change User s password Changing the date and time You can change the date and time of the PDU on the System DateTime window See Figure 35 Important Changing the PDU date and time affects other system...

Page 57: ...ents occur complete the following steps 1 From the main status page in the left navigation pane click Network SNMP 2 Click Trap Receivers to create a list of users or workstations that you want to rec...

Page 58: ...Figure 37 Changing the network configuration You can view or change the network configuration on the Network Configuration window To view or change the network configuration of the PDU complete the fo...

Page 59: ...f all events and a record of the PDU status System administrators can use summaries to analyze problems with network equipment Viewing the history log You can view the complete history of the PDU inpu...

Page 60: ...ewing the event log You can view the complete record of the PDU events on the Event Log window To view the complete record of the PDU events complete the following steps See Figure 39 1 From the main...

Page 61: ...the yellow LED to blink once 2 Push the reset button again for one second then wait for the yellow LED to blink once 3 Push the reset button again for one second then for the yellow LED to blink conti...

Page 62: ...aults 1 Push the reset button for more than three seconds then wait for the yellow LED to start blinking 2 Within the next 10 seconds while the yellow LED is blinking you must push and hold the reset...

Page 63: ...l area is likely to cause harmful interference in which case the user will be required to correct the interference at his own expense Properly shielded and grounded cables and connectors must be used...

Page 64: ...ponsibility for any failure to satisfy the protection requirements resulting from a non recommended modification of the product including the fitting of non IBM option cards This product may cause int...

Page 65: ...l Guide PDU 65 JIS C 61000 3 2 This statement applies to products greater than 20 A per phase three phase JIS C 61000 3 2 Japan Voluntary Control Council for Interference VCCI Notice A Korea Notice Pe...

Page 66: ...Copyright IBM Corporation 2020 Customer Install Guide PDU 66 Taiwan Notice IBM Taiwan Contact Information...

Page 67: ...Copyright IBM Corporation 2020 Customer Install Guide PDU 67 Regulatory and Compliance...

Page 68: ...ices offered in the U S A IBM Director of Licensing IBM Corporation North Castle Drive Armonk NY 10504 1785 U S A For license inquiries regarding double byte DBCS information contact the IBM Intellect...

Page 69: ...ms of the IBM Customer Agreement IBM International Program License Agreement or any equivalent agreement between us Any performance data contained herein was determined in a controlled environment The...

Page 70: ...d reports used in daily business operations To illustrate them as completely as possible the examples include the names of individuals companies brands and products All of these names are fictitious a...

Page 71: ...nforming to the application programming interface for the operating platform for which the sample programs are written These examples have not been thoroughly tested under all conditions IBM therefore...

Page 72: ...ountries Microsoft Windows Windows NT and the Windows logo are trademarks of Microsoft Corporation in the United States other countries or both Linux is a registered trademark of Linus Torvalds in the...

Page 73: ...echnical questions and information about products and prices please contact your IBM branch office your IBM business partner or your authorized remarketer When you send comments to IBM you grant IBM a...

Page 74: ...Copyright IBM Corporation 2020 Customer Install Guide PDU 74...

Page 75: ...Copyright IBM Corporation 2020 Customer Install Guide PDU 75 Part Number 03GJ008 Printed in Mexico...