SmartLogger1000
User Manual
8 Power Grid Scheduling
Issue 12 (2019-01-15)
Copyright © Huawei Technologies Co., Ltd.
261
Figure 8-7
Synchronizing the clock source
1.
Clock source
: Set
NTP
.
2.
Server
: Set the server IP address or domain name.
3.
NTP synchronization test
: Check the time synchronization status.
Set
Active power control mode
to
Remote output control
.
Figure 8-8
Remote Output Control
Control area
: Set the areas for remote output control. To enable the function in some areas, the
license needs to be imported and enabled.
Output control duration
: Set the time required for the inverter to change its output power from 0%
to 100% or from 100% to 0%.
PV plant ID
: Set the ID assigned by the power company to the SmartLogger.
Remote output control server
: Set the server IP address or domain name.
If the connection between the SmartLogger and the server is abnormal, obtain the output control file
in
.data
format from the website of the power company and import the file.
After the SmartLogger connects to the server, you can export the relevant file.
8.3 Reactive Power Adjustment
Before setting
Reactive power control mode
, set
Reactive power control
to
Enable
.