3 Commissioning Process
Airbridge BTS3606E&3606AE
System Commissioning Guide
3-30
Huawei Technologies Proprietary
Issue 02 (2006-10-10)
3.6.6 Mobile-Originated Packet Data Call Test
Ensure that the system uses dynamic rate allocation.
The test procedure is as follows:
Step 1
Register a test MS in the HLR.
Step 2
Prepare a BlueRose and keep an FTP server ready.
Step 3
Set up a connection between the test MS and the FTP server using the BlueRose and then
initiate an FTP uploading process.
Step 4
Observe the signaling messages and the state transition of the MS on BlueRose.
Step 5
Check the channel setup between the MS and the sector.
z
If the packet data service is unavailable after you log in to the FTP server, infer that the
MS is in dormant mode. If the packet data service is available, infer that the MS is in
active mode.
z
After an FCH is set up, the BTS sends ESCAM messages repeatedly and performs SCH
set-up or SCH extension repeatedly.
----End
3.6.7 Mobile-Terminated Packet Data Call Test
z
Ensure that the system uses dynamic rate allocation.
z
There are various test conditions listed in test steps. You can select some of them and perform the
test according to site conditions.
The test procedure is as follows:
Step 1
Register a test MS in the HLR.
Step 2
Prepare a BlueRose and keep an FTP server ready.
Step 3
Set up a connection between the test MS and the FTP server using the BlueRose and then
initiate an FTP uploading process.
Step 4
Test the downlink rate of a user under the conditions listed in Table 3-6.
Table 3-6 lists the conditions for testing the packet data downlink rate of a user.
Table 3-6
Conditions for testing the packet data downlink rate of a user
No. Status of
Adjacent
Cell
Status of
Destination
Sector
Status of MS
Distance from the
MS to the BTS
1
Not loaded
Not loaded
Static
Short
2
Not loaded
Not loaded
Static
Long
3
Not loaded
Not loaded
Moving at 15 km/h,
30 km/h, and 70 km/h
Long