3.4 O&M Test
Unless otherwise specified, carry out the following tasks at the BAM side.
Before the O&M test, ensure that the CCPM/CECM and the CMTR/OMTR works normally.
3.4.1 Querying Basic Information of the BTS
To query the basic information of the BTS, do as follows:
Step 1
Enter the following command:
LST BSCBTSINF
Step 2
Click
or press
Enter
.
Step 3
Specify the values of the parameters.
For example:
LST
BSCBTSINF
: BTSID=1;
Step 4
Click
or press
F9
to execute the command.
----End
3.4.2 Querying BTS Board Version
To query the BTS board version, do as follows:
Step 1
Enter the following command:
DSP CBTSBRDVER
Step 2
Click
or press
Enter
.
Step 3
Specify the values of the parameters.
For example:
DSP CBTSBRDVER:
BTSNAME="BTS", BTSID=1, BRDTP=BCKM,
BRDID=0;
Step 4
Click
or press
F9
to execute the command.
----End
3.4.3 Verifying the Software Version
The command
CHK CBTSSWVER
is used only for verifying the consistency between the running
software version of the BTS boards and the BAM version.
To verify the software version, do as follows: