![Honeywell TotalPlant LCN System Installation Download Page 40](http://html.mh-extra.com/html/honeywell/totalplant-lcn/totalplant-lcn_system-installation_152070040.webp)
LCN System Installation
4-4
9/96
4.2
STEP 3 Local Control Network (LCN) cables are grounded in two different schemes.
•
Systems with the 12.5 KHz system clock are self-grounding, by way of the cable
shield, when the cable is connected to the BNC receptacle on the CS/R paddle
board in the clock source node.
•
In systems with the 5 MHz bit digital system clock (a segment with only K2LCN
boards in the modules), the coax ground connection is made once for each cable
(A and B) by a wire from the KLCNA or KLCNB board to chassis ground. This
wiring is to be done in one module for each cable, preferably in the Module
designated as clock source modules.
In a segment that has had the processor board (EMPU, HMPU or HPK2)
replaced with K2LCN boards, the CS/R board must be retained but placed in an
empty slot in a module (the CS/R PWA is now used for grounding only).
If the system includes Hiway Gateway (HG) module(s) and a Hiway Traffic
Director (HTD), the Data Hiway cable shield grounding rules specified in the Data
Hiway Subsystem Site Planning manual must be followed. An overview of HG
preferred-access cabling is presented in Figure A-5.
If the system does not include the HTD, the Data Hiway cable shield is grounded
at the primary HG as follows: connect an AWG #14 wire from terminals 11 and
13 on terminal TB1 of the primary HG, DHI I/O board to the HG service post at
the bottom of the cabinet or station. See Figure 4-4. The HG service post must
be connected to Master Reference Ground (MRG) through AWG #4 wire.
The LCN cable connectors, like the Data Hiway cable connectors, must not be allowed to
touch the cabinet frame. All LCN cable connectors that enter or exit the cabinet or station
must be covered with heat-shrink tubing insulation.
Note that all LCN cable runs must be terminated the same way as the Data Hiway cables.
The 75-ohm terminators are interchangeable; however, the T-adapters are not.
NOTE
For LCN cable, use BNC T-adapter P/N 51190728-105 (Kings No. KC-99-52 or Amphenol 31-
208-1051). For Data Hiway cable, use BNC T-adapter P/N 30732055-001.
In an all K2LCN segment of an LCN coax system, a ground must be provided for the coax
shield by placing a wire between the grounding screw of the KLCN CA/KLCN CB boards
and the logic ground terminal on the back of a Dual Node module. This should only be
done at one point on each cable in a coax segment. Ground Cable A and Cable B in
different modules.
Verify the integrity of the system ground wiring after the system power has been connected
(see Section 7). Any grounding problems must be identified and immediately corrected to
eliminate the possibility of any of the following conditions:
• Shock hazard to personnel
• System operating problems
• Damage to equipment
Summary of Contents for TotalPlant LCN
Page 1: ...LCN System Installation SW20 500 ...
Page 2: ......
Page 3: ...LCN Installation LCN System Installation SW20 500 Release 510 CE Compliant 9 96 ...
Page 10: ...LCN System Installation iv 9 96 ...
Page 16: ...LCN System Installation 2 4 9 96 ...
Page 42: ...LCN System Installation 4 6 9 96 ...
Page 50: ...LCN System Installation 6 2 9 96 ...
Page 58: ...LCN System Installation 8 6 9 96 ...
Page 60: ...LCN System Installation 9 2 9 96 ...
Page 68: ...LCN System Installation 11 2 9 96 ...
Page 70: ...LCN System Installation 12 2 9 96 ...
Page 83: ...LCN System Installation 15 5 9 96 15 7 15052 Figure 15 6 Mounting of an Two LCN MAUs ...
Page 84: ...LCN System Installation 15 6 9 96 ...
Page 112: ...LCN System Installation B 6 9 96 ...
Page 128: ...LCN System Installation Index 4 9 96 ...
Page 130: ......
Page 131: ......