20 Commissioning
Honeywell
4
4. COMMISSIONING
Before commissioning, note the warnings and instructions listed in
Chapter 1!
4.1 COMMISSIONING STEPS OF SMARTDRIVE COMPACT
1
Read carefully the safety instructions in Chapter 1 and follow them.
2
After the installation, make sure that:
• both the inverter and the motor are grounded
• the mains and motor cables comply with the requirements given in Chapter
• the control cables are located as far as possible from the power cables
(see Chapter, step 2) and the shields of the shielded cables are connected
to protective earth.
3
Check the quality and quantity of cooling air (Chapter 3.1.2).
4
Check that all Start/Stop switches connected to the I/O terminals are in
Stop
-
position.
5
Connect the inverter to mains.
6
Run the Start Up Wizard (The Wizard is explained fully in chapter 9.11)
1. Activate the wizard by pressing STOP for 5 seconds
2. Tune the motor nominal speed
3. Tune the motor nominal current
4. Select the mode (0 = basic, 1 = Fan, 2 = Pump, 3 = Conveyor)
Or if the setting is done manually set the parameters of group 1 according to the
requirements of your application. At least the following parameters should be set:
• motor nominal voltage (par. 1.1)
• motor nominal frequency (par. 1.2)
• motor nominal speed (par. 1.3)
• motor nominal current (par. 1.4)
You will find the values needed for the parameters on the motor rating plate.