55
Install collar tie to the rafter with (3) 3" nails at each end
(Fig. A)
.
Starting at the wall with the door, install collar tie
BE
on the 1st rafter from the gable wall and then on
every
other
rafter, as shown.
FINISH
Your collar tie(s) are now installed.
3" (7,6 cm)
1
BEGIN
1st
1st
3rd
3rd
5th
1 x 3 x 96" (2,5 x 7,6 x 243,9 cm)
BE
HINT:
For best appearance, install
collar ties on back side of rafter.
Fig. A
PARTS REQUIRED:
COLLAR TIE INSTALLATION
x18
x12
x3
x2
10x10' 10x14'
Flush to roof
panel
GABLE WALL
GABLE WALL
3"
(7,6 cm)
Nails
10' x 10'
10' x 14'