If you have not chosen our concrete foundation (3M40420), please contact your supplier
for a professional foundation installation.
For the concrete foundation (3M40420) with the stainless steel pedestals 40mm
(3M40430), 100mm (3M40434) or 200mm (3M40431), the following installation
instructions apply:
1.
Once you have found an installation site that meets the
requirements (see page 17), the first step is to dig a hole
of size 0.45 m x 0.36 m x 0.8 m (L x W x H).
Make sure that the supply line is either from right or
left must be fed and suitably on which in the
foundation the intended pipeline. Straighten The
foundation must be level (horizontal).
2.
Lower the concrete foundation into the hole and guide the supply cable upwards
through the guide embedded in the concrete foundation. Make sure that the cables
protrude far enough so that an electrical connection can be made without any
problems.
3.
Now mount the pedestal (e.g. 40 mm) on top of the
concrete foundation and screw it tight with the enclosed
M12 screws. For the prescribed strength class 8.8, the
tightening torque should be about 90 Nm.
4.
Then close the gaps next to the concrete foundation
(e.g. with soil). Make sure that the pedestal remains level
(horizontal).
5.
Now place the cPP2 charging station on the stainless
steel pedestal. To do this, open the housing panel of the
charging pole via the swivel handle on the left side of the
cPP2. Place the charging pole in position above the
mounted pedestal. Insert the supply cables via the cable
opening in the base of the charging pole. Place the
charging pole on the pedestal so that the through holes
in the base plate of the charging pole are directly above
the threads in the pedestal. Screw the charging pole into
the pedestal with the four M8 x 20 hexagonal bolts supplied using the open-end
wrench.
Installation and operating manual
cPP2
charging pole
Version: 1.0.2