DANGER!
The above colour coding is NOT internationally binding: If the individual wires
in the supply cable are colour-coded differently, contact a qualified electrical
contractor! Have the supply line checked and replaced if necessary.
5
Make sure that the supply line is properly tightened and not under tension.
6
Switch on all internal circuit breakers in the charging pole (switch position I ON).
7
Close the cover of the column and lock it with the swivel handle.
ATTENTION!
For operation, it is recommended that you install cylinder locks in the swivel
handle of the charging pole to prevent unauthorised opening of the housing.
Commercially available 40 or 45 half-profile cylinders are suitable for
installation.
This completes the installation of your charging pole. The back-up fuse in the supply line
can be reactivated.
After the mechanical and electrical installation, your charging station is ready for operation.