A sufficiently dimensioned supply line for the power supply must be provided at the
mounting position. The supply line must be laid in the ground in coordination with
the pipe opening on the concrete foundation. If necessary, the supply line must be
protected against mechanical effects in the area in front of the foundation (by a
suitable hose or pipe).
•
For mechanical protection, suitable collision protection must be provided to protect
the end user from a possible collision with the charging pole.
•
One parking position for an end user must be provided on each side of the
charging pole. The minimum distance between the vehicle and the charging pole
should not be less than 45 cm and not more than 100 cm.
•
Select the location of the charging pole so that it is easily accessible for emergency
vehicles.
•
The cPP2 charging pole should not be installed in areas with a high volume of
people or on thoroughfares. In particular, ensure that the charging cables are laid in
a clearly visible position and that passers-by or walkways are NOT obstructed by the
cables.
•
In principle, the cPP2 is designed for operation in high ambient temperatures.
Nevertheless, it is recommended that, if possible, the charging pole is mounted so
that it is protected from direct sunlight: This prevents excessive heating of the
housing. Further information on ambient conditions can be found in the "Technical
data" section on page 31.
Socket installation
DANGER!
During the entire assembly, the circuit breakers for all supply lines to the
cPP2 must be deactivated: The supply lines must
IN EVERY CASE BE
CURRENTLESS
and may only be reconnected to the mains for the final
electrical commissioning.
NOTE!
To dehumidify the interior of the cPP2, we recommend filling the entire
pedestal area with dry granules: Minimizes the chance of undesirable
effects