INSTALLATION
MANUAL
EN
MI_020
Rev.1
29/04/2020
Page 12 of 24
Reinforced concrete
Mechanical anchoring
By way of example only, below is a list of some types of walls:
Proceed to fasten the ceiling plate using Hilti HSL-3-G M16/25 screw
anchors or other anchors with similar characteristics, carefully
following the instructions provided by the anchor manufacturers
and shown below for information purposes:
do
Nominal
drill
bit
diameter
Mt
Closing bending moment
t
Minimum drilling depth
Sw
Wrench opening
hs
Minimum
insertion
depth
x
Fastening height
l
Anchor tie-rod length
Anchor tie-rod
do
(mm)
t
(mm)
hs
(mm)
l
(mm)
Mt
(Nm)
SW
(mm)
x
(mm)
HSL-3-G M 16/25
24
125
100
163
80
24
25
1.
Apply the paper template at the Product installation point and
mark the fastening hole points with a pencil.
2.
Make the holes in the ceiling in accordance with the anchoring
tie-rod manufacturer’s specifications.
3.
Using a pump or a vacuum cleaner, remove the drilling residues
and dust from the hole.
4.
Fasten the Bar to the ceiling and, using a hammer, insert the
anchoring tie-rod in the hole.
Attention!
Check the fitting depth
5.
Using a torque wrench, tighten the anchorage to the tightening
force indicated by the screw anchor manufacturer.
The anchorage will immediately bear the weight.
6.
Proceed in the same way for the remaining anchors.
7.
After one hour, again tighten the tie-rods to the prescribed
tightening torque.
Summary of Contents for GIMAled81
Page 37: ...MANUALE D USO E MANUTENZIONE IT MU_027 Rev 1 29 04 2020 Pag 13 di 33 Modello a piantana...
Page 57: ...MANUALE D USO E MANUTENZIONE IT MU_027 Rev 1 29 04 2020 Pag 33 di 33 Note...
Page 94: ...OPERATION AND MAINTENANCE MANUAL EN MU_027 Rev 1 29 04 2020 Page 13 of 33 Mobile model...
Page 114: ...OPERATION AND MAINTENANCE MANUAL EN MU_027 Rev 1 29 04 2020 Page 33 of 33 Notes...