Condition(s)
Hazard / Measure
High temperatures
Circulatory collapse of passengers in the event of a defect in the hoist until
passengers are freed
. Take sufficient fluids along in the hoist. In the
case of open platform, wear/take sunscreen.
Ice/snow
Injury to passengers/people at the ground station/landing levels as a result
of snow breakage or icicles.
Falling on snow or ice.
Remove ice/snow from the platform, the roof of the platform, from
all access points, mast anchors / gear racks / cables/cable pot.
Do not use saline substances for this purpose.
Ensure that no roof avalanches / icicles can fall from the building
onto/into the platform or the access points. Remove hazards before
start-up. Wear a helmet.
Do not use open platform where there is a danger of roof
avalanches / icicles.
Ensure that all gates, hatches etc. are functional.
At the end of the working day, move the platform 20 cm upwards in
order to prevent the limit switches from freezing up.
In the case of large amounts/depths of snow: prevent car from
travelling as far as the layer of snow. Hoist could be damaged:
Storms/lightening/hail
Injury to people as a result of lightening or hail
Damage to the hoist as a result of strong gusts of wind/bolts of lightening.
Do not transport people.
Bring the platform down to ground level.
Flooding
Damage to the hoist as a result of running into a flooded pit. Loss of stability
of the foundation due to flooding.
Turn off electricity.
Pump pit dry.
Check foundation/buffer.
Check enclosure.
Sandstorm
Difficulty breathing / risk of suffocation in the event of long-term exposure,
e.g. in the event of a defect in the hoist. Carry a dust mask.
Damage to the hoist as a result of switch cabinets / filter pads becoming
blocked.
Clean switch cabinets / filter pads.
Fog
Injury to people as a result of parts projecting into the travel path.
Transportation of parts through the travel path of the hoist using a crane.
Use organisational measures to ensure that no parts project into
the travel path / that parts are not transported through the travel
path of the hoist.