Incoming Inspection and Verification
Part 17997
Rev. 6, March 2011
6-3
• One 7/64-in (2.8 mm) Allen key with a short L-shape handle (part number 10011)
• One blue protective cap for the H201 sensor
• One roll of Teflon tape
6.1.3
Inspecting
Verify the Hydran 201T
i
completely as outlined below.
1.
Using the shipping list (see Section 6.1.2 on page 6-2), ensure all items are present.
2.
Inspect the following components for any visual damage (bump, scratch or others):
• The enclosure
• The brass adaptor
• The Hydran 201 sensor
• The CPU module
• The input/output (I/O) module
3.
Verify the ac power supply voltage (indicated on the left side of the I/O module)
corresponds to the power source voltage and the value on the Test Certificate and
Data Sheet (for an example, see Figure 6-1 on page 6-4). The left side is determined
by facing the H201T
i
’s display and keypad. There are two possibilities:
• 115 V, corresponding to a 90–132 Vac range from 47 to 63 Hz
• 230 V, corresponding to a 180–264 Vac range from 47 to 63 Hz
4.
Verify the type and size of the supplied flanged brass adaptor:
• 1-in NPT (outside diameter 1.25 in [32 mm]): See Figure B-4 on page B-3.
• 1.5-in NPT (outside diameter 1.75 in [44 mm]): See Figure B-3 on page B-2.
• 1.5-in NPT finned for high temperatures: See Figure B-6 on page B-4.
• 2-in NPT (outside diameter 2.25 in [57 mm]): See Figure B-5 on page B-4.
Summary of Contents for Hydran 201i
Page 1: ...GE Energy Services Digital Energy Hydran Instruction Manual 201i System ...
Page 6: ...Instruction Manual vi Rev 6 March 2011 Part 17997 PAGE LEFT INTENTIONALLY BLANK ...
Page 8: ...Instruction Manual viii Rev 6 March 2011 Part 17997 PAGE LEFT INTENTIONALLY BLANK ...
Page 22: ...Instruction Manual xxii Rev 6 March 2011 Part 17997 PAGE LEFT INTENTIONALLY BLANK ...
Page 36: ...Chapter 1 Introduction 1 10 Rev 6 March 2011 Part 17997 PAGE LEFT INTENTIONALLY BLANK ...
Page 114: ...Chapter 5 Before Installation 5 16 Rev 6 March 2011 Part 17997 PAGE LEFT INTENTIONALLY BLANK ...
Page 143: ...Installation Part 17997 Rev 6 March 2011 6 29 Figure 6 9 Installing the CPU Module ...
Page 236: ...Chapter 12 Troubleshooting 12 20 Rev 6 March 2011 Part 17997 PAGE LEFT INTENTIONALLY BLANK ...
Page 244: ...Chapter 13 Maintenance 13 8 Rev 6 March 2011 Part 17997 PAGE LEFT INTENTIONALLY BLANK ...
Page 254: ...Appendix B Mechanical Drawings B 2 Rev 6 March 2011 Part 17997 Figure B 3 1 5 In Adaptor ...
Page 255: ...Hydran 201Ti Intelligent Transmitter Part 17997 Rev 6 March 2011 B 3 Figure B 4 1 In Adaptor ...