7. Operation
7.1 General conditions
Before carry out any operation on the equipment, it is necessary to have a thorough knowledge of the
chapter and the
functions that might have been enabled in the installation process.
The equipment operates automatically without the aid of an operator; the operating state should be controlled through the equipment’s
instrumentation.
ATTENTION –
A
The interpretation or variation of some data is reserved exclusively for specialized and qualified staff.
During operation, make sure that environmental and storage conditions have not changed over time and that the equipment is not exposed
to adverse weather conditions (see
chapter).
7.2 Commissioning
Before proceeding with commissioning, make sure that you have
carried out all the checks and verifications indicated in the previous
chapters.
This inverter can be powered both with DC or (only in case PVS-
100/120 PRE-CHARGE BOARD KIT is installed) AC sources. In
case of DC source is used, make sure that irradiation is stable
and adequate for the inverter commissioning procedure to be
completed.
At the first activation of the inverter the firmware version could be
syncronized between power module and wiring box. During this
phase the LEDs “Power” “Alarm” and “GFI” blinks together every 1
second. This process is absolutely normal and must be completed
without interruption. A switch-off of the system during this process
could cause serious damage to the inverter.
Do not place objects of any kind on the inverter during operation!
Do not touch the heat sink while the inverter is operating! Some
parts may be very hot and could cause burns.
Commissioning can be carried out in two different ways:
• Via Fimer Installer for Solar Inverters APP
Recommended mobile APP for commissioning a single inverter
as well as a multi-inverter solar plant.
• Via Web UI (access point wireless network)
Web User Interface enabling the parameters
settings and to perform commissioning of a single
inverter (multi inverter support is not provided).
Recommended as alternative method for performing single
inverter commissioning.
7.2.1 Commissioning via Installer for Solar
Inverters mobile APP
“Installer for Solar Inverters” is the new advanced Fimer mobile
APP that allows to simplify commissioning, setting parameters
and to make troubleshooting of Fimer string multi-inverters in large
scale solar plants.
Even in case of single inverter installation it can be consider the
most suitable professional tool to be used.
“Installer for Solar Inverters” mobile APP is available for mobile
devices with an Android version of 6.0.1 or greather (iOS mobile
devices support will come soon) and could be downloaded and
installed from Play Store.
Commissioning procedure:
It’s highly recommended to connect the inverters in ethernet daisy
chain (with or without ring) before executing the commissioning
procedure.
Make sure that all the inverter being commissioned features the
last firmware version (the update can be executed via Installer for
Solar Inverters mobile APP).
The main steps to complete the commissioning procedures are
listed below:
• Install the “Installer for Solar Inverters mobile APP” on mobile
device.
• Login to the Aurora Vision installer account.
NOTE –
D
The account can be created in the mobile APP by
following the dedicated wizard procedure.