Faithtech FT68200 Operation Manual
53
Figure 3-20 DISC TEST
3. Configure the paramters according to your needs;
4. Press
to start discharge test;
5. When finished, the total discharge power, discharge energy and discharge time
will be prompted on screen.
Parameter Explanation
Name
Explain
Disc Mode
Selectable CC, CR, CP
Disc Curr
Set the current value when selected CC discharge mode
Disc Resi
Set the resistance value when selected CR discharge mode
Disc Powe
Set the power value when selected CP discharge mode
End Volt
Stop the test when battery voltage is below set parameter
End Capa
Stop test once accumulated discharge power reaches this figure
End Time
Step test once accumulated discharge time reaches this figure
3.19. OCP Test
The load has an over-current test function (OCP), and its measurement principle is: when
the input voltage reaches the turn-on voltage, there is a delay for a period of time, and the
constant current mode starts to work. At regular intervals, increase the load current
according to the step value and monitor the input voltage at the same time. If the input
voltage is higher than the end voltage, continue to test; if the input voltage is lower than
the end voltage, the previous maximum load current will be used as the measurement
result, then close the input and stop the test. The FT68200 series load provides an OCP
current judgment function, which can judge the range of the measurement result and
report PASS or FAIL.
Operation Procedure
1. Press
(Test) to go to “Test” function selection;
Summary of Contents for FT68200 Series
Page 9: ...Faithtech FT68200 Operation Manual 3 1 3 2 7U 8kW 10kW 12kW...
Page 10: ...Faithtech FT68200 Operation Manual 4 1 3 3 11U 14kW 16kW 18kW...
Page 11: ...Faithtech FT68200 Operation Manual 5 1 3 4 14U 20kW 22kW 24kW...
Page 12: ...Faithtech FT68200 Operation Manual 6 1 3 5 20U 30kW 36kW...
Page 13: ...Faithtech FT68200 Operation Manual 7 1 3 6 26U 42kW 48kW...
Page 14: ...Faithtech FT68200 Operation Manual 8 1 3 7 32U 54kW 60kW...