Hardness Tester
Startup
DuraJet 10
2-9
2.5
Initial Startup
Connections on the units
1
Hardware interface (option)
2
USB connection
3
Ethernet interface
4
Control unit connection
5
Control unit connection
6
Mains connection
7
Fuses
8
Main ON/OFF switch with indicator lamp
Turn the main switch to OFF.
Plug the connector of the fixed control unit cable into the connection on the control
unit.
Ensure that the control unit cable is firmly screwed into place.
Plug the power cable into the mains connection.
Plug the opposite end of the power cable into a grounded electrical outlet with a
protective earth conductor contact.
Turn the main switch to ON.
To release the EMERGENCY OFF button on the control unit, turn it clockwise.
The software starts the initialization process.
Connecting the unit