INSTALLING OPTIONS AND ACCESSORIES
Eaton Power Xpert 9395P-1200 UPS (1200 kVA, 1200 kW) Installation and Operation Manual
S
P-164000500 Rev 4
www.eaton.com/powerquality
5-9
5.3
Installing an Optional Remote Monitor Panel II
To install RMP II wiring:
1.
Verify the UPS system is turned off and all power sources are removed. See
Chapter 7, “UPS Operating Instructions,” for shutdown instructions.
2.
Perform the procedure listed in paragraph 5.1.
NOTE
If mounting to a hollow wall, secure the enclosure to a wood or metal stud within the wall. Do not
use hollow wall anchors.
3.
Securely mount the RMP II at the desired location. See Figure 5‐12 for mounting
hole locations.
NOTE
When installing signal wiring for CAN card J3 terminals, conduit must be installed between the
device and the UPS cabinet.
4.
Remove the ISBM cabinet top right interface conduit landing plate to drill or
punch conduit holes (see Figure 4‐16).
5.
Reinstall the conduit landing plate.
6.
Install conduit between the UPS and RMP II. See Figure 5‐12 for RMP II
knockout hole location.
7.
Install wiring between the UPS and RMP II. See Figure 5‐2 and Table 5‐1 for the
Powerware Hot Sync CAN Bridge Card terminal location and wiring information,
and Figure 5‐7, Figure 5‐8, and Table 5‐5 for the RMP II terminal location and
wiring information.
NOTE
120 Vac for the RMP II should be supplied from the critical bus by facility planners or the customer.
8.
9.
Close the front door and secure the latch.
10.
Restart the UPS. See Chapter 7, “UPS Operating Instructions,” for startup
instructions.
Summary of Contents for Power Xpert 9395P-1200
Page 195: ......
Page 196: ... P 1640005004 P 164000500 4 ...