© Danfoss 05-2011
AK-EM 100 Installation Guide
4
RC8BX402
The first part of the procedure is to establish connections between the gateway and controllers to allow the
data to be fed into the AK-EM 100.
Commissioners should already have a plan of the store to be commissioned, and so should have at their
disposal all of the required settings and addresses for connecting to local networks, gateway settings,
port numbers, passwords etc. This process should then be just a case of entering data to match the
requirements
From the main menu, select the
Commission Toolbox
to enter the main setup options page. The toolbox
contains several sections which should be executed in a certain order for the process to be completed
successfully.
The Commission Toolbox is comprised of 4 sections:
1. Gateway Details
The Gateway Details section contains information regarding the set up of the Gateways. From here,
multiple gateways can be added and configured to the AK-EM 100, as well as the connection addresses to
the gateway. There is also a link to the advanced settings options.
2. Network Communications
Once the Gateways are set up, this section is where the runs are made to detect and connect to the
controllers which are available in the Gateway. When connected, a table will be displayed which contains
the assets found in the network.
3. Additional Tasks
Additional Tasks contains links to pages which need to be carried out once the connection has been
successfully completed. These include configuring the assets, setting up user accounts, and building the
store mimic.
4. Site Details (Ethernet)
The final section contains fields for entering addresses for connecting the AK-EM 100 to a local server.
1. Establish Network Connection
Hint
Use the Event Log in the
Administration section
to view a list of actions
and changes carried
out within the system,
including those actions
within Commissioner’s
Toolbox.
1.1 The Commission Toolbox