PIM00411
5-1
Chapter 5
Start-up Procedure
Start-up Procedure are as follows.
1.
Check
・・・・・・・・・・・・・・・・・・・・・・・・・・・・・
Refer to “Chapter 6 Confirmation of the Arrival Product”
2.
Transportation and installation
・・・・・・・・・・
Refer to “Chapter 7 Transportation and Installation”
3.
Piping
・・・・・・・・・・・・・・・・・・・・・・・・・・・・・
Refer to “Chapter 8 Piping”
4.
Electric wiring
・・・・・・・・・・・・・・・・・・・・・・・
Refer to “Chapter 9 Electric Wiring”
5.
Turning on the power
・・・・・・・・・・・・・・・・・
Refer to “Chapter 10 Test Run”
Please make sure the following items firstly and turning on the
power.
Is it already correctly installed?
Is it already correctly plumbed?
Is the hydraulic oil injected?
Is it already correctly wired?
Is the power supply voltage correct?
6.
Flushing running
・・・・・・・・・・・・・・・・・・・
Refer to “Chapter 10 Test Run”
7.
Oil replacement
・・・・・・・・・・・・・・・・・・・・・
Refer to “Chapter 10 Test Run”
8.
Air vent
・・・・・・・・・・・・・・・・・・・・・・・・・・
Refer to “Chapter 10 Test Run”
9.
Operation check
・・・・・・・・・・・・・・・・・・・
Please check the operation of the actuator. Please refer to “11.5
Setup mode”, change the setting value of the pressure and flow rate