6
|
Unit installation
Installer reference guide
64
EPRA14~W1 + ETVH/9W(G)
Daikin Altherma 3 H HT F
4P587502-1A – 2020.01
6.2.7 To close the indoor unit
1
Close the cover of the switch box.
2
Put the switch box back into place.
3
Reinstall the top panel.
4
Reinstall the side panels.
5
Reinstall the front panel.
6
Reconnect the cables to the user interface panel.
7
Reinstall the user interface panel.
NOTICE
When closing the indoor unit cover, make sure that the tightening torque does NOT
exceed 4.1 N•m.
6.3 Mounting the outdoor unit
6.3.1 About mounting the outdoor unit
When
You have to mount the outdoor unit before you can connect the water piping.
Typical workflow
Mounting the outdoor unit typically consists of the following stages:
1
Providing the installation structure.
2
Installing the outdoor unit.
3
Providing drainage.
4
Installing the discharge grille.
5
Protecting the unit against snow and wind by installing a snow cover and baffle
plates. See
"6.1 Preparing the installation site"
6.3.2 Precautions when mounting the outdoor unit
INFORMATION
Also read the precautions and requirements in the following chapters:
▪
"1 General safety precautions"
▪
"6.1 Preparing the installation site"
6.3.3 To provide the installation structure
Check the strength and level of the installation ground so that the unit will not
cause any operating vibration or noise.
Fix the unit securely by means of foundation bolts in accordance with the
foundation drawing.