Chapter 7
7777
Installation check
Installation check
7
Now that you have installed the system, you can test it to verify it is ready
for customer delivery. Follow the check lists below to test the system for
proper operation.
•
Installation check list: Antenna
•
Installation check list: ACU, connectors and wiring
•
Installation check list: Functional test in harbor
7.1
Installation check list: Antenna
Step
Task
Further information
Done
1.
Check that the antenna is free of
obstructions.
See
2.
Make sure there is sufficient
space for access through the
service hatch.
See
3.
Make sure to maintain the
vertical orientation of the ADU
center line.
4.
Check that the ADU is installed
where vibrations are limited to a
minimum.
5.
Check that you programmed the
blocking zones correctly.
See
and
Setting up blocking zones
(RX and TX)
6.
Make sure that the safety
distance for radiation hazard of
30 metres is kept.
See
7.
Check that the mounting height
of the antenna is in accordance
with the ship’s min. roll period.
See
Table 7-1: Installation check list: Antenna
SAILOR900TM.book Page 1 Monday, September 16, 2013 11:01 AM
Summary of Contents for Sailor 900 VSAT
Page 2: ...98 138976 A Cover_SAILOR 900 VSAT System_407090B indd 2 15 04 2013 15 54 39 ...
Page 28: ...List of tables xxvi 98 133966 G1 SAILOR900TM book Page xxvi Monday September 16 2013 11 01 AM ...
Page 257: ...Appendices SAILOR900TM book Page 1 Monday September 16 2013 11 01 AM ...
Page 258: ...SAILOR900TM book Page 2 Monday September 16 2013 11 01 AM ...
Page 355: ...98 138976 A Cover_SAILOR 900 VSAT System_407090B indd 3 15 04 2013 15 54 40 ...