Installation Guide_PV-ezRack_SolarTerraceIII-A_AU_V2.0
1/10 Duerdin Street, Clayton VIC 3168 Australia
Tel: +61 3 9239 8088 Fax: +61 3 9239 8024
E-mail: [email protected] www.clenergy.com.au
19
page
of 28
Installation Instruction
5.2.3 If the T Rail is not long enough, connect two T Rails together using the Splice for the T-110 Rail
as shown in the diagram below.Insert half of the Splice into the T Rail and fasten with two sets of Self-
tapping screws in each side of the T Rail, and then insert the other Splice into the T Rail and again
fasten with Self-tapping screws.To prevent thermal expansion problems, the Rails shall not exceed
30m long.
5.2.4 Place the T Rails one by one in the planned position on the supports.
Insert half of Splice into the T Rail
Insert half of the Splice into the T Rail
Then use two sets of Self-tapping
screws in each side of the T Rail
Two sets of Self-tapping screws
each side of the T Rail
NOTE: Please fasten the Self-tapping screw until the rubber washer grips firmly, attaching
the T Rails tightly onto the splice.
Fig. 16
Fig. 17