Installation Guide_PV-ezRack_SolarTerraceIII-A_AU_V2.0
1/10 Duerdin Street, Clayton VIC 3168 Australia
Tel: +61 3 9239 8088 Fax: +61 3 9239 8024
E-mail: [email protected] www.clenergy.com.au
24
page
of 28
Installation Instruction
Step 4 When using as Inter Clamp, click the
Universal Clamp into the channel of T Rail and
then slightly lift the framed PV Module to make
sure the Grounding Clip of Universal Clamp is
fully covered as shown in Figure 26.
Fig. 26
Step 3 Place the first PV Module on the T Rails and position the Universal Clamp as an End Clamp
to fix it and then fasten lightly with Allen Key. Make sure the frame of the PV Module is fully in contact
with the Universal Clamp as shown in Figure 25. Visually check the Universal Clamp and PV module
are correctly installed.
Fig. 25
Step 5 Place the next framed PV Module into the
other side of Universal Clamp. Make sure the
Grounding Clip of the Universal Clamp will be fully
covered and ensure the frame of PV Module is
closely in contact with Universal Clamp as shown
in Figure27.Note the 20mm gap when using
Universal Clamps.
20
Fig. 27