Installation Guide_PV-ezRack_SolarTerraceIII-A_AU_V2.0
1/10 Duerdin Street, Clayton VIC 3168 Australia
Tel: +61 3 9239 8088 Fax: +61 3 9239 8024
E-mail: [email protected] www.clenergy.com.au
15
page
of 28
Installation Instruction
Fig. 1
Fig. 2
Fig. 3
To achieve the earthing/
grounding function, fasten
the M8 nut within 18-20
N·m
To achieve the earthing/
grounding function, fasten
the M8*40 bolt within 13-
14 N·m
Fig. 4
Fig. 5
5.1 Pre-assembled Support Installation (For 30 degree tilt support)
5. Installation Instruction
Solution 1
Step 1:
Unfold the pre-assembled support as shown in
Figure 2;
Step 2:
Unfold the Slotted Al-Tube as shown in Fig.3;
Step 3:
Unlock the M12*100 bolts from the H Joint first and
fasten the Al-Tube and H Joint lightly with M12*100
again as shown in Fig.4;
Step 4:
Rotate the L-anchor and U-anchor plates to ensure
tthey align as shown as Fig. 5.
NOTE: The bolt heads have to be kept in same
direction.
5.1.1 Unfold the Pre-assembled Support