Sweep the top surface of the foundation vault free of dirt and debris.
Install the isolation mat onto the top surface of the vault
Note:
For improved cabinet sealing, you can flip the isolation mat so that it covers the large rectangular and AC
cut outs in the base of the cabinet or riser, cut holes in the mat where the cables/conduit enter, and then seal
the cable entry locations after completing Step 5 below.
Using two people, lift the cabinet or battery compartment riser directly above its mounting position on the pad.
Slowly lower the cabinet or riser onto the pad, keeping the mounting holes in the cabinet base aligned with the
anchor studs (or holes) in the pad.
Note:
If properly aligned, the entry ducts should slide down over the conduits as the cabinet or riser
lowers. If necessary, trim the conduit down to a height that enables it to pass into the entry duct.
Pull the earth ground wire into the cabinet or riser through one of the cable entry ducts.
Anchor the cabinet or riser to the pad as follows:
a.
Get four anchor bolts, four flat washers, and four lock washers from the installation kit.
b.
Install one flat washer, lock washer, and anchor bolt into each of the four threaded mounting inserts.
c.
Tighten the bolts to secure the cabinet to the pad.
Verify that the doors open and close freely. If necessary, use shims to level the cabinet or riser.
Apply silicone caulking to the bottom perimeter of the cabinet or riser.
Step 1:
Step 2:
Step 3:
Step 4: