Chapter 7: Turning Up the Cabinet Power System
This chapter describes how to turn up and test the cabinet power system.
This process includes checking the cabinet ground connection, checking the AC power supply voltage, installing rectifier
modules into the rectifier shelf, installing batteries for reserve power, and turning up and testing the DC power system.
Topics Covered
This chapter covers the following topics:
• Turning up the cabinet power system (local power)