37
ENGLISH
EN
4 - OPERATION
4.1 - Commissioning
• Make sure that the heat exchangers do not operate under
conditions that are severer than the design conditions (pres-
sure, temperature, flow rate, fluid type).
• Make sure that the tightening dimension matches that shown
on the nameplate. Never tighten beyond this dimension.
• Open the valves slowly to avoid water hammering and ther-
mal shock.
Sudden changes in temperature or pressure as well as sudden
inrushes of hot fluid in a cold unit (or vice versa) may damage
the gaskets and plates and cause leaks.
• Make sure that the heat exchanger is not subject to vibrations or
frequent short cycles.
• Purge air from the two circuits completely after circulating the flu-
ids. Air left inside the circuits may cause product overheating, re-
duce the exchanger’s efficiency and increase the risks of corrosion.
4.2 - Post-commissioning tests
After running the system for one hour:
• Check for signs of leaks. Weak flow rates, however, are nor-
mal during commissioning.
• Check the pressures and temperatures of all the fluids being
circulated.
5 - MAINTENANCE
• All maintenance operations must be carried out by qualified,
trained personnel.
• The heat exchanger may not be altered in any way without
CIPRIANI’s consent.
• As the maintenance intervals depend on a multitude of
parameters (fluids, temperatures, etc.), the frequency of
preventive maintenance is left to the operator’s judgment.
Nevertheless, a maintenance inspection is recommended at
least once a year.
• Periodically check the condition of the corrosion protection
coatings and apply touch-ups as needed.
5.1 - Preventive maintenance
• Our experience shows that, when used under normal oper-
ating conditions, gasketed heat exchangers have a service
life of over 10 years. We advise against opening them too
often.
• Inquire about applicable environmental standards and pre-
vailing legislation, particularly regarding the frequency of
checks and what to do in the event of a leak.
• Once a year, test the operation of all safety devices, check
the condition of the insulation, look for signs of external cor-
rosion and test the pressure on the heat exchanger outlet.
• Record all periodic checks and problems in the mainte-
nance log.
Summary of Contents for S020+
Page 124: ...124 1 2 60 C CIPRIANI CIPRIANI PED 2014 68 PED 2014 68 CIPRIANI...
Page 125: ...125 RU CIPRIANI...
Page 126: ...126 0 C CIPRIANI CIPRIANI 1 1b 2...
Page 127: ...127 RU 1a 1b 2...
Page 128: ...128 1 2 3 4 5 6 7 8 9 10 11 12...
Page 129: ...129 RU TS PS PT PED 2014 68 CE PED 2014 68 I II III IV CE II III IV 1 2 d d...
Page 131: ...131 RU 60 C 0 C 60 C 500 5 7 4 2 4...
Page 132: ...132 TF PB...
Page 133: ...133 RU CIPRIANI 10...
Page 134: ...134 1 2 3 4 1 2 3 4 4 1 5 CIPRIANI 1 2 3 4 11 5 6 Plug In...
Page 136: ...136 1 2 40 C 3 4...
Page 138: ...138 CIPRIANI 6 Plug In 7 Plug In Plug In 8 Plug In 5 7 1 A 7 6...
Page 139: ...139 RU Plug In 9 b 5 7 3 Plug In Plug In 9 5 7 3 Plug In 5 7 1 Plug In DN200 2 3 5 2 ACS 8 9...
Page 140: ...140 10 11 CIPRIANI PS 10 Fig 10 Fig 11...
Page 144: ...144 CIPRIANI CIPRIANI...
Page 145: ...145 RU CIPRIANI NBR EPDM FPM HNBR...
Page 146: ...146 Note...
Page 147: ...147 Note...