background image

40. Remove blower access panel from front of unit and reinstall

on rear of unit. Reinstall rear blower panel on front of unit.
Reinstall top of unit. Install patch plates on front center panel
and seal all remaining holes as necessary.

41. Reconnect wiring to blower motor, gas valve, pressure

switches, and limit switches using unit wiring diagram. (See
Fig. 17.) Ensure all wiring is properly connected and tight.

NOTE:

Upon completing the installation, pressure test the fur-

nace (using the following procedure) as critical gaskets/seals have
been broken.

PRESSURE TEST

Do not place the unit into operation without checking the
system pressures of the unit as outlined in this procedure.
Failure to follow the pressure test procedure may result in a
non- operational unit, nuisance tripping and/or a condition
which may lead to personal injury.

1. Check wiring to insure it is properly connected and tight.

2. Place a jumper wire across pressure switches to bypass both

controls.

3. Turn gas valve off.

4. Set room thermostat above room temperature.

5. Turn on electrical supply to furnace.

6. Check pressures at:

a. Induced-draft motor tap (located at top left of motor

casing).

b. Tube previously labelled "top of coil."

c. Tube previously labelled "bottom of coil."

Excessive variation of the pressures listed in Table 7 indicates
a system leak and/or blockage. This is especially true of the
induced-draft motor pressure. An induced-draft motor pres-
sure in the 1.5-in. to 1.6-in. wc range of vacuum pressure
indicates a leak in the system and/or excessive vent length.
Corrective action must be taken before the unit is placed into
operation. Failure to take corrective action may result in a
non-operational unit, condensate leakage, nuisance tripping,
premature unit failure, and/or a condition which may lead to
personal injury.

7. Use Table 7 to verify a properly-sealed unit.

NOTE:

The pressures listed are for an ambient temperature of

approximately 76°F. These pressures may vary slightly due to
temperature, vent configuration, and vent length. The table is a
general guideline of system pressures and may vary slightly from
unit to unit.

Table 7—Unit Pressures (In. wc)

UNIT SIZE/

VENTING

INDUCED-DRAFT

MOTOR

PRESSURE

TOP OF COIL

PRESSURE

BOTTOM OF

COIL

PRESSURE

50/Min Vent

Max Vent

2.5
2.5

0.32
0.32

0.94
0.94

75/Min Vent

Max Vent

2.5
2.0

0.37
0.58

1.45
1.50

100/Min Vent

Max Vent

2.4
2.2

0.23
0.29

1.50
1.50

125/Min Vent

Max Vent

2.5
2.3

0.28
0.38

1.60
1.70

8. Reconnect pressure switch tubing as shown in Fig. 13.

9. Turn off electrical supply to unit.

10. Remove jumper wire on pressure switches.

11. Turn on gas valve.

12. Turn on electrical supply to unit. Unit should begin ignition

cycle.

Step 11—Start-up, Adjustment, and Safety Check

GENERAL — The furnace must have a 115-v power supply
properly connected and grounded. Proper polarity must be main-
tained for correct operation. Thermostat wire connections at R, W,
Y, G, and C must be made at the 24-v terminal block on the control
board. The gas service pressure must not exceed 0.5 psig (14-in.
wc), but must be no less than 0.16 psig (4.5-in. wc) for natural gas.

The unit must not be installed, operated, and then turned off
and left turned off in an unoccupied structure during cold
weather when the temperature drops to 32°F and below.
Freezing condensate left in the furnace will damage the
equipment. See Service and Maintenance Instructions for
winterizing procedure.

SEQUENCE OF OPERATION — Using the schematic diagram in
Fig. 17, follow the sequence of operation through the different
modes. This furnace has a unique control system—read and follow
the wiring diagram very carefully.

1. When thermostat "calls for heat", the R-W circuit closes.

a. Ignition sequence—Power from the transformer energizes

the fan control board. The fan control energizes the
induced-draft blower motor. Pressure switches P1 and P2
normally open contacts close to initiate the ignition se-
quence.

b. Ignition trial—The ignition control energizes the pilot gas

valve. The ignition electrode begins sparking to light the
pilot. When the pilot flame is sensed, the main gas valve
opens and the pilot flame lights the burners. If the pilot
flame is not sensed, the ignition control locks out after 90
sec. Reset the ignition control by turning the thermostat
below room temperature for 1 minute and then above room
temperature.

c. Blower on delay— The fan control starts the blower after

30 sec. The blower on delay is not adjustable.

d. Blower off delay—When the thermostat is satisfied, the

circuit between R and W is broken, de-energizing the gas
valve and stopping gas flow to the burners. The blower
motor remains energized 60, 90, 120, or 150 sec depending
on the blower off delay selection (factory shipped set for
60-sec delay).

2. Cooling mode.

The thermostat "calls for cooling" closing R and R-Y circuits.
The R-Y circuit starts the outdoor condensing unit, and the
combined R-Y and R-G circuit starts the furnace blower motor
on cooling speed. The (EAC) terminals are energized with
115v whenever the blower is operating.

When the thermostat is satisfied, the R and R-Y circuits are
broken. The furnace blower will continue operating on cooling
speed for an additional 90 sec.

START-UP PROCEDURES

1. Fill condensate trap with water.

a. Disconnect condensate drain tube from bottom of inducer

housing.

11

Summary of Contents for 101 Series

Page 1: ...ther than wood The design of this furnace line is not A G A certified for installation in recreational vehicles manufactured housing mobile homes or outdoors Before installing this furnace refer to the current edition of the NFGC NFPA 54 1992 ANSI Z223 1 1992 which is available from the National Fire Protection Association Inc Batterymarch Park Quincy MA 02269 American Gas Association 1515 Wilson ...

Page 2: ...n UNIT SIZE 050 075 100 AND 125 Sides 0 Back 0 Top of Plenum 0 Vent Connector PVC Pipe 0 Front Casing 1 Front Service 30 Zero in with controls on front of furnace 1 in from back of elbow with combustion air inlet on back of furnace and 1 in from end of inducer motor with controls located on back of furnace Measured from end of inducer motor Table 2 Dimensions In UNIT SIZE LENGTH WIDTH WEIGHT LB 05...

Page 3: ...TION RELATIVE TO COOLING EQUIP MENT The cooling coil must be installed parallel with or on the downstream side of the furnace to avoid condensation in the heat exchanger When installed parallel with a furnace dampers or other means used to control the flow of air must prevent chilled air from entering the furnace If the dampers are manually operated they must be equipped with a means to prevent op...

Page 4: ... with appropriate straps hangers etc Use a minimum of 1 hanger every 6 ft Joint compounds pipe dope should be applied sparingly and only to the male threads of the joints This pipe dope must be resistant to the action of propane gas Install a sediment trap in the riser leading to the furnace The trap can be installed by connecting a tee to the riser leading to the furnace so that the straight thro...

Page 5: ...4 V WIRING Make field 24 v connections at the 24 v termi nal block Connect Y terminal as shown in Fig 4 for proper cooling operation The 24 v terminal board is marked for easy connection of field wiring See Fig 5 NOTE Use AWG No 18 color coded copper thermostat wire for lengths up to 100 ft For wire lengths over 100 ft use AWG No 16 wire ACCESSORIES Install accessories per manufacturer s instruc t...

Page 6: ...Standards COMBUSTION AIR AND VENT PIPING The combustion air and vent pipe fittings must conform to American National Standards Institute ANSI standards and American Society for Testing and Materials ASTM standards D1785 schedule 40 PVC D2665 PVC DWV D2241 SDR 21 and SDR 26 PVC D2661 ABS DWV or F628 schedule 40 ABS Pipe cement and primer must conform to ASTM standards D2564 PVC or D2235 ABS See Tab...

Page 7: ...ing such as when it passes through an unheated space or when a chimney is used as a raceway the pipe must be insulated with 1 2 in thick Armaflex type insulation When the combustion air pipe is installed above a suspended ceiling the pipe must be insulated with 1 2 in Armaflex type insulation The combustion air pipe should also be insulated when it passes through a warm humid space Solvent cements...

Page 8: ...lation level or grade whichever is greater b Minimum of 4 ft clearance must be provided from electric or gas meters regulators and relief equipment 4 Install 90 elbows as shown in Fig 6 or 7 or use a 180 U fitting 5 Install tee as shown in Fig 6 or 7 6 Check required dimensions as shown in Fig 6 or 7 7 Disassemble loose pipe fittings Clean and cement fittings using same procedures as outlined for ...

Page 9: ...ield reversal be sure to have a correct wiring diagram available and be prepared to mark all wires as they are disconnected The inducer assembly burner controls gas valve and electrical controls are designed to be field reversed as necessary for certain field installations and applications per the following procedure 1 Remove manifold cover plate and air inlet plate burner re moval cover 2 Disconn...

Page 10: ...all vent return pipe so pipe outlet is facing rear of unit Reinstall 4 washers and nuts securing pipe to heat exchanger bottom plate Remove and discard cardboard previously placed between fins and pipe Remove patch plate and cut insulation on rear center panel and position vent return pipe through panel Secure pipe to panel with 4 screws 30 Remove blower motor wiring harness strain relief from fro...

Page 11: ...umper wire on pressure switches 11 Turn on gas valve 12 Turn on electrical supply to unit Unit should begin ignition cycle Step 11 Start up Adjustment and Safety Check GENERAL The furnace must have a 115 v power supply properly connected and grounded Proper polarity must be main tained for correct operation Thermostat wire connections at R W Y G and C must be made at the 24 v terminal block on the...

Page 12: ... 34 35 36 3 2 3 3 3 7 890 38 39 3 4 3 7 37 38 39 3 2 3 5 3 8 37 38 3 3 3 6 37 38 3 4 3 8 36 37 3 2 3 5 36 37 3 3 3 6 36 37 3 4 3 7 36 3 5 35 36 3 2 3 6 905 38 39 40 3 3 3 6 3 8 38 39 3 4 3 7 37 38 39 3 2 3 5 3 8 37 38 3 3 3 6 37 38 3 4 3 8 36 37 3 2 3 5 36 37 3 3 3 6 36 37 3 4 3 7 36 37 3 5 3 8 920 38 39 40 3 2 3 4 3 7 38 39 40 3 3 3 6 3 8 38 39 3 4 3 7 37 38 39 3 2 3 5 3 8 37 38 3 3 3 6 37 38 3 4...

Page 13: ... pressure item c and replace the main burner orifices as needed Refer to NFGC Appendix F Table F 4 for proper orifice sizing at high altitudes 8 Proceed to item c to adjust manifold pressure c Adjust gas input NOTE The gas meter must always be clocked with the burner enclosure front installed The gas valve has been nominally set at 3 5 in wc for natural gas 1 Remove burner enclosure front and cap ...

Page 14: ...selector located at the blower motor See Table 10 Table 10 Blower Speed Selection SPEED TAP NO Common 1 High 2 Medium 3 Low 4 Recheck the temperature rise It must be within limits specified on the unit rating plate Recommended operation is at midpoint of rise or above 3 Set thermostat heat anticipator The thermostat heat anticipator must be set to match the amp draw of the components in the R to W...

Page 15: ...drain safety switch This control ensures the condensate drain is open to allow condensate flow and that combustion air is flowing through the unit prior to starting the ignition cycle The blocked drain safety switch has only 1 tube connected to it Check switch operation as follows a Place unit into operation with burners on b Pinch off tube leading to pressure switch P2 The burners should shut off...

Page 16: ...D DISCONNECT ON HOT LEG 1 2 3 4 60 SEC 90 SEC 120 SEC DELAY OFF SCREW SETTINGS 150 SEC MED HI GND N2 HEAT COOL N3 D1 N4 C BI S1 S2 M2 K1 K2 K2 K3 X R Y C W G CN23 2 CN23 1 CN23 6 LIMIT CONTROL TRANSFORMER CONDENSING UNIT PRESSURE SW N O N C PS1 PS2 V1 CN23 3 CN23 5 COM ST912081005 ELECTRONIC FAN TIMER ROS MV PV MV PV MV MV PV PV 24V GNO GNO BURNER SPARK GAS VALVE HONEYWELL VR8204 PILOT 24V IGNITIO...

Reviews: