54733-10BA2L
1 – 116
02.2017
9 Radiation Protection
Volume 1
9.2.2
Radiation Exposure during Installation of the
Shielding
The shieldings of measuring systems are usually designed such that
the limit of the control area is in a given distance (in most cases less
than one meter) around the shielding, and it does not matter
whether point or rod sources are being used and how high their
activity is. A simplified calculation of the radiation exposure during
installation of the shielding is possible with sufficient accuracy using
the dose rate data printed on the type plate, measured in 1 m dis-
tance from the shielding. The radiation exposure D can be calcu-
lated according to the following formula:
D = DR x t x 4
D = accumulated dose during assembly in Sv
DR = dose rate on the type plate of the shielding in µSv/h
t = time needed for the installation with shielding in h
If the work process is prepared well, you may expect a working
time of less than 20 minutes to perform work such as installation of
the shielding or operating the shutter.
Calculation example
DR = 3µSv
t = 20min (1/3h)
D = 3 x 1/3 x 4 = 4µSv/h
If we compare this dose with the permissible annual dose of 1 mSv
for persons who are not exposed to radiation on their job, this work
may be carried out 250 times per year by one and the same person.
Summary of Contents for LB 480
Page 2: ......
Page 11: ...1 g l Time 0 00 10 30 11 00 11 3012 00 12 30 Volume 1 Safety Manual...
Page 12: ...54733 10BA2L 1 12 02 2017 Volume 1...
Page 22: ...54733 10BA2L 1 22 02 2017 4 Transport and Assembly Volume 1...
Page 56: ...54733BA26 1 56 02 2017 5 Explosion Protection Volume 1...
Page 57: ...SENSseries LB 480 BERTHOLD TECHNOLOGIES GmbH Co KG 1 57 Volume 1 5 Explosion Protection 1...
Page 58: ...54733BA26 1 58 02 2017 5 Explosion Protection Volume 1...
Page 59: ...SENSseries LB 480 BERTHOLD TECHNOLOGIES GmbH Co KG 1 59 Volume 1 5 Explosion Protection 1...
Page 60: ...54733BA26 1 60 02 2017 5 Explosion Protection Volume 1...
Page 61: ...SENSseries LB 480 BERTHOLD TECHNOLOGIES GmbH Co KG 1 61 Volume 1 5 Explosion Protection 1...
Page 62: ...54733BA26 1 62 02 2017 5 Explosion Protection Volume 1...
Page 63: ...SENSseries LB 480 BERTHOLD TECHNOLOGIES GmbH Co KG 1 63 Volume 1 5 Explosion Protection 1...
Page 64: ...54733BA26 1 64 02 2017 5 Explosion Protection Volume 1...
Page 66: ...54733BA26 1 66 02 2017 5 Explosion Protection Volume 1...
Page 67: ...SENSseries LB 480 BERTHOLD TECHNOLOGIES GmbH Co KG 1 67 Volume 1 5 Explosion Protection 1...
Page 68: ...54733BA26 1 68 02 2017 5 Explosion Protection Volume 1...
Page 69: ...SENSseries LB 480 BERTHOLD TECHNOLOGIES GmbH Co KG 1 69 Volume 1 5 Explosion Protection 1...
Page 70: ...54733BA26 1 70 02 2017 5 Explosion Protection Volume 1...
Page 71: ...SENSseries LB 480 BERTHOLD TECHNOLOGIES GmbH Co KG 1 71 Volume 1 5 Explosion Protection 1...
Page 72: ...54733BA26 1 72 02 2017 5 Explosion Protection Volume 1...
Page 73: ...SENSseries LB 480 BERTHOLD TECHNOLOGIES GmbH Co KG 1 73 Volume 1 5 Explosion Protection 1...
Page 108: ...54733 10BA2L 1 108 02 2017 7 Functional Safety Volume 1 7 13 Functional Safety Certificate...
Page 110: ...54733 10BA2L 1 110 02 2017 7 Functional Safety Volume 1...
Page 112: ...54733 10BA2L 1 112 02 2017 8 Visual Inspection Volume 1...
Page 128: ...54733 10BA2L 1 128 02 2017 9 Radiation Protection Volume 1...
Page 147: ...SENSseries LB 480 Level measurement BERTHOLD TECHNOLOGIES GmbH Co KG 1 147 Volume 1 1 Notes...
Page 149: ...1 g l Time 0 00 10 30 11 00 11 3012 00 12 30 Volume 2 Installing SENSseries...
Page 150: ...54733 10BA2L 2 150 02 2017 Volume 2...
Page 170: ...54733 10BA2L 2 170 02 2017 1 System Description Volume 2...
Page 240: ...54733 10BA2L 2 240 02 2017 4 Repair Maintenance and Upkeep Volume 2...
Page 288: ...54733 10BA2L 2 288 02 2017 5 Technical Information Volume 2...
Page 297: ...SENSseries LB 480 Level measurement BERTHOLD TECHNOLOGIES GmbH Co KG 2 297 Volume 2 2 Notes...
Page 299: ...1 g l Time 0 00 10 30 11 00 11 3012 00 12 30 Volume 3 Operation with HART Communicator...
Page 300: ...54733 10BA2L 3 300 02 2017 Volume 3...
Page 390: ...54733 10BA2L 3 390 02 2017 3 Getting Started via the HART Communicator Volume 3...
Page 410: ...54733 10BA2L 3 410 02 2017 6 Functional Processes Volume 3...
Page 428: ...54733 10BA2L 3 428 02 2017 7 Explanations Volume 3...
Page 440: ...54733 10BA2L 3 440 02 2017 8 Error Handling Volume 3...
Page 444: ...54733 10BA2L 3 444 02 2017 9 Setup Protocol Volume 3 Path Parameters Unit Standard SETUP...
Page 445: ...SENSseries LB 480 Level measurement BERTHOLD TECHNOLOGIES GmbH Co KG 3 445 Volume 3 3 Notes...
Page 449: ...SENSseries LB 480 Level measurement BERTHOLD TECHNOLOGIES GmbH Co KG 1 449 Volume 1 Notes...