Installation
Compliance voltage testing is best done before installation. See “Determining an SVI Positioner
Compliance Voltage in a Control System” on page 97.
The steps necessary to complete the SVI II ESD installation and software setup are outlined in
Table 1.
WARNING
Failure to adhere to the requirements listed in this manual may
cause loss of life and property.
Before installing, using, or carrying out any maintenance tasks
associated with this instrument, READ THE INSTRUCTIONS
CAREFULLY.
Table 1: SVI II ESD Installation Steps
Step No.
Procedure
Reference
1
Attach mounting bracket to the
actuator.
See page 25 for rotary valve and
page 30 for reciprocating valve
instructions.
2
Install the SVI II ESD magnetic assem-
bly (rotary valves only).
See page 25 for instructions.
3
Assemble the SVI II ESD on the bracket
that is mounted to the valve actuator.
See page 25 for rotary valve and
page 30 for reciprocating valve
instructions.
4
Connect the pneumatic tubing to the
SVI II ESD.
See page 35 for instructions.
5
Connect the air supply to the SVI II
ESD.
See page 39 for instructions.
6
Install the wiring for the SVI II ESD.
See page 40 for instructions.
7
Connect the PST controller to the
HART
®
Control Loop segment by
installing the SVI II ESD wiring.
See page 42 for instructions.
8
Power up the SVI II ESD.
See page 44 for instructions.
9
If appropriate, configure/calibrate
using ValVue ESD
See page 62 and page 66 for
instructions.
If appropriate, configure/calibrate
using a HART
®
Hand Held
Communicator
See page 67 for instructions.