Opera ting Ma nua l a nd Inspection Book
SMART LIFT 2.30 SL, 2.35 SL, 2.40 SL / HYMAX S 3000, 3500, 4000
20110015 OPI
49
Version 1.0
7.5 Checking the stability of the lift
•
Retighten nuts of the approved fastening anchors to the torques specified by the manufacturer
using a pre-set torque wrench. (Torque details are found on the data sheet of the corresponding
anchor manufacturer)
8 Assembly and commissioning
Figure 20:
8.1 Set up guidelines
•
Lift set up is done by trained manufacturer personnel or a contract partner. Set up is to
be done according to the assembly instructions.
•
A standard lift may not be set up in explosion endangered spaces or wash halls.
•
Before setting up, ensure or make a sufficient foundation.
•
A level set up space is to be done in all cases, where open air and enclosed foundations
where frost is expected, must have a frost-depth thickness.
•
An on-site standard electrical connection of 3 ~/N + PE, 400 V, 50 Hz is to be provided.
The supply is to be secured according to VDE0100 with 16 ampere fuses. The minimum
wire cross-section is 2.5 qm².
•
The cable guide is possible through the riser with cross-beam or through the hole in the
baseplate. In all cases, prevent kinks or tensional loads on the cable.
•
After successful lift installation and before first commissioning, the operating company
must have the lift grounding conductors inspected on-site according to IEC regulation
(60364-6-61). An insulation resistance test is also recommended.
8.1.1 Set up and anchoring the lift
On-site provision of suitable auxiliary materials (e.g. forklifts, crane, etc.) are to be
made available for unloading the lift and for assembly.
Before setting up the lift, the operating company must ensure or make a sufficient foundation. For
this, a normal reinforced concrete floor with a value of a min. C20/25 (B25) is required. The
minimum foundation thickness (without screed and tiles) is to be taken from the general
foundation plan in this document.
In our plans, we inform of the minimum specifications for the foundation, however local conditions
(e.g. underground, floor quality, etc.) are outside of our responsibility. In special cases, the design
of the installation location must be individually specified by planning architects and statics
experts. Open air foundations must be made to frost depth.
The operating company of the lift is solely responsible for the set up location.
If the lift is to be assembled on an existing concrete floor, cement quality and strength are to be
checked beforehand. In case of doubt, make a test bore and insert an anchor. Then, tighten the
anchor to the manufacturer recommended torque.