Opera ting Ma nua l a nd Inspection Book
SMART LIFT 2.30 SL, 2.35 SL, 2.40 SL / HYMAX S 3000, 3500, 4000
20110015 OPI
32
Version 1.0
Figure 3: To release the fixture plate, the rear lever must be
pushed.
•
The lifting arm block must be ratcheted in after the fixture point has been reached.
•
After each set down of the vehicle, check the lifting arm positions below the fixture points
again and adjust as required.
•
Check that there are no people or objects in the hazardous area of the lift.
5.2
Lifting the vehicle
•
Lift the vehicle until the wheels are off the ground. Actuate operating element => "Lift" (see
image 4)
•
If the wheels are not blocked, interrupt the lifting process and check for proper seating of
the carrier plate.
•
Afterwards, lift the vehicle to the desired working height.
Ensure secure vehicle placement on the carrier plate, otherwise there is a danger of the
vehicle dropping.
The lift can be controlled several times depending on the load distribution during
"lifting".
See to it that the lifting arm blocks are ratcheted in after the vehicle has been
accepted.
Figure 4
Operating unit with reversing switch
(2.30 SL to 2.40 SL)
Operating element of the 2.50 SL
On-site a separate lockable main switch must be placed at a reachable height if the electrical
connection of the lift and electrical interface is higher than 1.90 m and can only be reached with
assistance (e.g. a ladder)!
Optional
CE-Stop button