• Verify ozone generator (if so equipped) is functional. 10 minutes after engaging the sanitation cycle there will
be a strong ozone smell inside the cabinet indicating that the ozone generator is functional. The UV lamp inside
the ozone generator must be replaced annually – see chapter “Replace Ozone Generator Lamp”, call the parts
department at American Panel Corporation to order new lamps.
• Verify Wi-Fi connection (if so equipped) is functional.
• Turn unit off, wipe down exterior.
• On the remote condensing unit perform the maintenance procedure recommended by its manufacturer.
• Inform the customer and the factory if any functional and performance issues were found following the completion
of the above tests.
• Complete inspection paperwork and verify consumer has all necessary operation manuals, menus, and
instructions. Contact factory with any questions, Monday-Friday 8:00 a.m. to 5:00 p.m. ET at 800-327-3015 or
consult the website at www.AmericanPanel.com
The above maintenance procedure should be done yearly and is not a substitute for an efficient
local maintenance schedule such as daily, and quarterly maintenance schedule.
Maintenance & Cleaning
Annual Maintenance Checklist - continued