5.2.8 J-Bus PCB
CAUTION
When one unit on the databus chain is disconnected, the other units on that databus are also disconnected.
Replace
1. Make sure that all power to the equipment is OFF. See §
Prepare: Switch OFF power supply
2. Disconnect the cables and the ground wire from the J-Bus PCB (B).
3. Remove the four screws (A). Use a number 5.5 socket wrench.
4. Replace the J-Bus PCB (B).
5. Install the four screws (A). Use a number 5.5 socket wrench.
Connect
6. Connect the cables to the connectors:
•
LMC to P6;
•
J-Bus control for Bus A to P1 and P2;
•
J-Bus control for Bus B to P3 and P4;
•
Earth wire to the ground terminal.
7. Close the cabinet door.
8. Check the remote control functions.
9. Configure the flashing system. See §
.
10. Close the cabinet door.
5.2.9 Capacitor
Prepare
1. Make sure that all power to the equipment is OFF. See §
Prepare: Switch OFF power supply
2. Wait minimum 1 min. after all power to the equipment is OFF.
Flashing System Maintenance
Maintenance
42
Copyright
©
ADB Safegate, All Rights Reserved
Summary of Contents for FCU-1-in-1
Page 2: ......
Page 8: ...Flashing System Maintenance TABLE OF CONTENTS viii Copyright ADB Safegate All Rights Reserved ...
Page 18: ...Flashing System Maintenance Safety 8 Copyright ADB Safegate All Rights Reserved ...
Page 28: ...Flashing System Maintenance Introduction 18 Copyright ADB Safegate All Rights Reserved ...
Page 42: ...Flashing System Maintenance Commissioning 32 Copyright ADB Safegate All Rights Reserved ...
Page 64: ...Flashing System Maintenance Maintenance 54 Copyright ADB Safegate All Rights Reserved ...
Page 106: ...Flashing System Maintenance Technical data 96 Copyright ADB Safegate All Rights Reserved ...
Page 110: ......