127
Preparing the rack for server installation
1
Install eight distands into the vertical rails of the system rack.
2
Adjust the front bracket to the preferred length.
(1) Turn the captive thumbscrews counterclockwise to loosen
them.
(2) Slide the front bracket to the preferred length.
(3) Secure the front bracket in its preferred position by turning
the captive thumbscrews clockwise.
Do the same thing to the other front bracket.
Summary of Contents for Altos G540 Series
Page 1: ...Acer Altos G540 Series User s Guide ...
Page 10: ...x ...
Page 11: ...1 System tour ...
Page 24: ...1 System tour 14 System boards Mainboard ...
Page 34: ...1 System tour 24 ...
Page 35: ...2 System setup ...
Page 44: ...2 System setup 34 ...
Page 45: ...3 System upgrade ...
Page 78: ...3 System upgrade 68 ...
Page 79: ...4SystemBIOS ...
Page 108: ...4 System BIOS 98 ...
Page 109: ...5 System troubleshooting ...
Page 120: ...5 System troubleshooting 110 ...
Page 121: ...Appendix A Server management tools ...
Page 129: ...Appendix B Rack mount configuration ...
Page 130: ...This appendix shows you how to set up the Altos G540 server in a rack mount configuration ...