Fig. 13 NTC connection
Step 7:
fasten the waterproof cover using 4 screws.
If battery different than Pylontech are used contact ZCS technical support.
4.4.
Grid Connection
Step 1
: Loosen 4 screws (part A) using a screwdriver (fig. 14)
Step 2
: Remove the waterproof cover (part B), loosen the cable gland (part C), then remove the stopper (part G)
Step 3
: Route a 3-wire power cable through GRID cable gland, then connect the 3 wires to the corresponding
terminal blocks. (BROWN – L, BLUE – N, YELLOW/GREEN – PE)
Step 4
: Fasten the waterproof cover using 4 screws.
Fig. 14 Grid & Load connection