ActiveScale™ P100 Support Guide
72
5.2 Installing
scale
up Storage Nodes
Base system Storage Nodes and scale up Storage Nodes are installed in the same way. Scale up kits are
installed bottom to top, as shown.
For more information regarding Storage Node installation, refer to
Adding Storage Nodes to the rack
Figure 5-1. ActiveScale P100 system layout
5.2.1 Cabling a scaled up system
Once the Storage Nodes are added to the ActiveScale P100 system, the only other hardware-based step is
to connect the data cables.
The 10G DAC cables included in the scale up kit have both blue and green labels. The label colors indicate
the location of the associated Storage Node and System Interconnect port.
Table 5-2. 10G DAC cable reference
For more information, refer to
5.3 Software steps for a scale up addition
Scaling up
allows you to expand the capacity of your system by adding a new column (in other words, a
scale up kit) to each system in your deployment. Each system must have identical scale up and scale out
configurations. Follow this procedure after you have completed the hardware steps for a
single
scale up kit.
For hardware steps, see the
ActiveScale P100/ActiveScale X100 Installation Guide
.
Cable type
Number of labels
Label color
Storage node location
Base system
Two
Yellow
Storage column one
Scale up kit
Four
Two green
Storage column two
Two blue
Storage column three
Содержание ActiveScale P100
Страница 103: ...ActiveScale P100 Support Guide 101...
Страница 104: ...ActiveScale P100 Support Guide 102...
Страница 120: ...ActiveScale P100 Support Guide 118...
Страница 124: ...ActiveScale P100 Support Guide 122...
Страница 131: ...ActiveScale P100 Support Guide 129...
Страница 132: ...ActiveScale P100 Support Guide 130...