Installation overview
The installation section, is provided in the following order.
1. Installation: Part 1 (Physical)
2. Installation: Part 2 (Electrical power)
3. Installation: Part 3 (Fluid path)
4. Installation: Part 4 (Control system connections and wiring)
5. Installation: Part 5 (Setting the pump up (general))
6. Installation: Part 6 (Setting the pump up (specific - control system))
Follow the installation in the order above. This is to ensure the pump:
l
Cannot topple over after installation of the pumphead,
l
Cannot be tilted beyond 20 degrees (maximum slope of installation).
l
Has electrical power prior to the first time pumphead installation procedure, and general set up of
pump.
9 INSTALLATION OVERVIEW
47
Содержание qdos 20
Страница 40: ...6 Storage 6 1 Storage conditions 41 6 2 Shelf life 41 6 STORAGE 40...
Страница 169: ...Procedure 9 NEXT 10 Use keys to set Alert Level Procedure 11 SELECT to return to FLUID LEVEL SETTINGS 16 OPERATION 169...
Страница 192: ...NOTICE The pumphead locking lever is designed to be loosened or tightened by hand 17 MAINTENANCE 192...