30
INTELLIZONE2 INSTALLATION MANUAL
In the following procedure, check for proper calls on the
Status Screen.
System Checkout
1.
Set all of the zone thermostats to the cooling mode.
2.
Reduce the cooling set point to 1° below the actual
zone temperature on all thermostats.
3.
First stage cooling should energize after a delay.
4.
Be sure the compressor and blower are activated.
Check that the zone, cool, and fan speed LEDs are on.
5.
Decrease the cooling set point two more degrees and
check to see that the fan speed increases and second
stage cooling is energized. Using the AID tool, check the
fan speed and compare to the Blower Speed tables.
6.
In variable speed applications, when operating in low
compressor speeds, ensure that there is adequate air
flow from each register so as to get sufficient throw into
the conditioned space. If there is not sufficient airflow, try
increasing the selected blower speed.
7.
Adjust the thermostats until the temperature displayed is
5° higher than the actual temperature on all thermostats.
8.
The call for cooling should be canceled after a delay.
9.
Set all of the zone thermostats to the heating mode.
10. Increase the heating set point to 1° above the actual
zone temperature on all thermostats.
11. After a delay, the unit should start up in the first stage
heating mode (H1). Using the AID tool, check the fan
speed and compare to the Blower Speed tables.
12. Increase the heating set points two more degrees and
check to see that the fan speed increases and second
stage heating is energized (H2). Using the AID tool
check the fan speed and compare to the Blower Speed
table.
13. Increase the heating set point to 4° above the actual
zone temperatures. Be sure the auxiliary heat is
energized and the fan speed increases. Using the AID
tool check the fan speed and compare to the Blower
Speed tables.
14. Set system to maintain desired comfort level.
15. Instruct the owner/operator of correct thermostat and
system operation.
16. Fill out and forward all warranty registration papers
to WaterFurnace.
System Startup and Checkout cont.
NOTE:
Unit check out can be accomplished by going to the
Test Mode screen at the MasterStat and selecting Central
Zone. The system will be controlled only by the MasterStat.
Any time superheat and subcooling is being checked, the
zone system must be in the central zone mode.
Blower Speed Tables
Single or Dual Capacity
Heating
Unit Call
Blower Level Call
(Norm)
Blower Level Call
(Dehumid)
H1
55 or 70%
N/A
H2
85 or 100%
N/A
H2, W
Aux Blower
N/A
W
Aux Blower
N/A
G
G Only (Cont Blower)
N/A
Cooling
Unit Call
Blower Level Call
(Norm)
Blower Level Call
(Dehumid)
C1
55 or 70%
55 or 70% less 15% cfm
C2
85 or 100%
85 or 100% less 15% cfm
G
G Only (Cont Blower)
G Only (Cont Blower)
Variable Speed Capacity
Heating
Unit Call
Blower Level Call
(Normal Staging Shown)
Blower Level Call
(Dehumid)
H1 or H2
25%
N/A
H3 or H4
40%
N/A
H5 or H6
55%
N/A
H7 or H8
70%
N/A
H9 or H10
85%
N/A
H11 or H12
100%
N/A
H9-H12, W
Aux Blower
N/A
W
Aux Blower
N/A
G
G Only (Cont Blower)
N/A
Cooling
Unit Call
Blower Level Call
(Norm)
Blower Level Call
(Dehumid)
C1 or C2
25%
25% less 15% cfm
C3 or C4
40%
40% less 15% cfm
C5 or C6
55%
55% less 15% cfm
C7 or C8
70%
70% less 15% cfm
C9 or C10
85%
85% less 15% cfm
C11 or C12
100%
100% less 15% cfm
G
G Only (Cont Blower)
G Only (Cont Blower)
IntelliZone2 Configuration
Once added to the Aurora control system, the setup and
configuration mode should be entered at the MasterStat by
holding a finger on the IntelliZone2 logo for 5 seconds. The
Configuration and Setup mode will appear automatically.