Ultra Installation Guide v2.0
31
Customer Support
1.800.366.5343 –
VZ0022UG201509-2.0
33.
Turn the Unit OFF with the Switch located at the Control Box door.
34.
Install the Base and Top Covers of the Column with the supplied screws.
35.
Route, to the upper cable access of the Generator Cabinet, the cables from the Column to be
connected in the Generator (HV Cables, Stator/ Thermostat, if applicable AEC and Bucky signal
cables).
Generator Installation:
Prior to beginning installation, it is recommended to inspect the site and verify that the X-ray room
complies with Pre-installation requirements, such as:
• Incoming Line Power.
• Main Switch and Safety Devices.
• Conduits.
• Space Requirements.
Verify U24 chip is for Vizion (b39 or b75) (Presto is b13, b17, or b22)